Question 60
A server operations team encounters the following situation: An installation team plans to lift a populated 3U server alone into the top rails in violation of site safe-lift guidance. Which sustained operational control best reduces the likelihood of this same issue recurring?
Explanation
Correct Answer
This control targets the underlying recurrence risk: Unsupported manual handling presents a preventable installation safety risk. It builds validation into the affected workflow and supports the expected recovery result: Equipment is secured without injury or damage during a supervised lift.
Incorrect Answers
This control addresses a different scenario: A new 10GbE NIC is fitted with a 1GbE-only SFP module, and a storage transfer cannot reach its specified link rate. That event's root mechanism was the installed pluggable is not capable of the intended link speed. The described incident instead arises from: Unsupported manual handling presents a preventable installation safety risk.
This control addresses a different scenario: A heavy UPS is planned above lightly loaded servers in a rack that maintenance technicians frequently roll across a raised floor. That event's root mechanism was high center of gravity and unverified floor loading create a personnel and stability hazard. The described incident instead arises from: Unsupported manual handling presents a preventable installation safety risk.
This control addresses a different scenario: Technicians install an active 10GbE optical link using a multimode transceiver at one end and a single-mode optic at the other. That event's root mechanism was mismatched transceiver and fiber specifications prevent a valid optical link. The described incident instead arises from: Unsupported manual handling presents a preventable installation safety risk.