Question 180
An organization lists 30 initiatives but has not applied cost, benefit or risk comparisons. Which architecture focus or activity most directly addresses the stated need, rather than a merely adjacent issue?
Explanation
Correct Answer
Prioritize migration projects using business value, dependencies, costs and risk in Phase F. The practical check is whether approved sequence shows why high-value enablers precede lower-priority work.
Incorrect Answers
Phase D technology gaps is concerned with identifying technology gaps and roadmap components in Phase D. The requirement in this case is different: prioritizing migration projects using business value, dependencies, costs and risk in Phase F.
ADM phase relationships is concerned with treat Requirements Management as continuous across all ADM phases. The requirement in this case is different: prioritizing migration projects using business value, dependencies, costs and risk in Phase F.
Phase H performance is concerned with monitoring business and technical performance as part of Architecture Change Management. The requirement in this case is different: prioritizing migration projects using business value, dependencies, costs and risk in Phase F.