Question 160
Two application teams want inconsistent synchronization patterns for the same customer profile updates. Which area of architecture work best describes the response needed in this situation?
Explanation
Correct Answer
Define application interaction patterns and integration requirements during Phase C. The practical check is whether interfaces show which service publishes changes and how consumers reconcile them.
Incorrect Answers
Phase C data governance is concerned with address data stewardship and lifecycle requirements in Data Architecture. The requirement in this case is different: defining application interaction patterns and integration requirements during Phase C.
Phase A sponsorship is concerned with establishing the architecture project and confirm business sponsorship in Phase A. The requirement in this case is different: defining application interaction patterns and integration requirements during Phase C.
Phase F roadmap confirmation is concerned with confirming and update the Architecture Roadmap during Phase F. The requirement in this case is different: defining application interaction patterns and integration requirements during Phase C.