Question 200
A project finishes go-live but never validates whether delivered services realize target architecture outcomes. Which area of architecture work best describes the response needed in this situation?
Explanation
Correct Answer
Conduct post-implementation review and closure activities in Phase G. The practical check is whether acceptance findings compare implementation results with approved architecture and outcomes.
Incorrect Answers
Phase H performance is concerned with monitoring business and technical performance as part of Architecture Change Management. The requirement in this case is different: conducting post-implementation review and closure activities in Phase G.
Phase A high-level picture is concerned with producing a high-level Architecture Vision describing the intended change. The requirement in this case is different: conducting post-implementation review and closure activities in Phase G.
Phase D baseline platform is concerned with documenting Baseline Technology Architecture in Phase D. The requirement in this case is different: conducting post-implementation review and closure activities in Phase G.