McAfee-Secured Website

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

100% PRINCE2 PRINCE2 7 Practitioner Guaranteed Success With Testking Training Materials

Get Real PRINCE2 7 Practitioner Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 78

Question 770

Following the agreed corrective action for this project concern—A city records migration meets all delivery metrics, but the project manager requests closure without documented user acceptance of the migrated records.—which evidence would verify a suitable outcome?

  1. The business receives an authorized closure report and retained records of delivered and outstanding work.
  2. The lessons report is accepted and relevant improvement owners are named.
  3. The board receives an acceptance record tied to the approved project product description.
  4. The board decision rests on verified safety acceptance rather than a claimed task completion.

Explanation

Correct Answer

C:

This finding directly demonstrates the intended result: The board receives an acceptance record tied to the approved project product description. It tests whether the chosen remediation—Obtain authorized user acceptance or formally resolve deficiencies before recommending closure.—has addressed the cause: The closing project process has not confirmed acceptance of products against their criteria.

Incorrect Answers

A:

The offered finding is relevant when premature closure lacks controlled preservation, handover and contractual accountability. Here the acceptance test must show that the board receives an acceptance record tied to the approved project product description.

B:

The offered finding is relevant when the closing process omits lessons reporting needed to improve future projects. Here the acceptance test must show that the board receives an acceptance record tied to the approved project product description.

D:

This result could confirm a fix when the completion recommendation is inconsistent with the actual acceptance status of a critical product. It would not demonstrate that the board receives an acceptance record tied to the approved project product description.

Question 771

Which management-control deficiency underlies the following situation? A city records migration meets all delivery metrics, but the project manager requests closure without documented user acceptance of the migrated records.

  1. The closing report does not provide a reliable assessment of overall project performance.
  2. Project closure is being confused with completion of all future benefit realization.
  3. The closing project process has not confirmed acceptance of products against their criteria.
  4. Closing activities have not resolved or transferred remaining issues as actionable follow-on work.

Explanation

Correct Answer

C:

The identified root cause is: The closing project process has not confirmed acceptance of products against their criteria. The appropriate correction is: Obtain authorized user acceptance or formally resolve deficiencies before recommending closure. A separate validation must then show: The board receives an acceptance record tied to the approved project product description.

Incorrect Answers

A:

The mechanism could explain a fault where the closing report does not provide a reliable assessment of overall project performance; it does not account for the current condition, where the closing project process has not confirmed acceptance of products against their criteria.

B:

This diagnosis fits a situation in which project closure is being confused with completion of all future benefit realization. Here, the closing project process has not confirmed acceptance of products against their criteria.

D:

The cause in this option would matter if closing activities have not resolved or transferred remaining issues as actionable follow-on work. The reported failure instead arises because the closing project process has not confirmed acceptance of products against their criteria.

Question 772

The project team has corrected the following defect: A city records migration meets all delivery metrics, but the project manager requests closure without documented user acceptance of the migrated records. Which future assurance check should be added?

  1. Apply proportionate controlled closure steps even when a project is stopped early.
  2. Reconcile final-stage product status against acceptance records before closure.
  3. Make operational handover and support acceptance closure prerequisites.
  4. Include signed user acceptance in the closing-project checklist.

Explanation

Correct Answer

D:

The lasting control is: Include signed user acceptance in the closing-project checklist. It addresses recurrence of this mechanism: The closing project process has not confirmed acceptance of products against their criteria. A successful system should still demonstrate: The board receives an acceptance record tied to the approved project product description.

Incorrect Answers

A:

The option addresses cases in which premature closure lacks controlled preservation, handover and contractual accountability. In the reported incident, the closing project process has not confirmed acceptance of products against their criteria instead.

B:

This measure addresses a risk where the completion recommendation is inconsistent with the actual acceptance status of a critical product. The recurring failure here arises because the closing project process has not confirmed acceptance of products against their criteria.

C:

This measure addresses a risk where project closure is being proposed before a controlled handover to operations. The recurring failure here arises because the closing project process has not confirmed acceptance of products against their criteria.

Question 773

The following project-management situation requires a decision: A regional transport platform finishes implementation but the support team has not accepted ownership of ongoing incidents and service levels. What should the team do?

  1. Complete or formally resolve the inspection and update the end project report before seeking closure.
  2. Agree operational ownership, support information and transition acceptance before closure authorization.
  3. Prepare the end project report with actual performance against the authorized baselines and outstanding benefit actions.
  4. Use the closing process in a tailored premature-closure form to document products, costs, obligations and lessons.

Explanation

Correct Answer

B:

The case requires this change: Agree operational ownership, support information and transition acceptance before closure authorization. The actual failure mechanism is: Project closure is being proposed before a controlled handover to operations. A meaningful acceptance check is: The service owner signs off operational readiness and responsibilities are recorded.

Incorrect Answers

A:

The option would help when the completion recommendation is inconsistent with the actual acceptance status of a critical product, but it would not address a situation where project closure is being proposed before a controlled handover to operations.

C:

“Prepare the end project report with actual performance against the authorized baselines and outstanding benefit actions” is useful when the closing report does not provide a reliable assessment of overall project performance. It does not resolve the current problem, in which project closure is being proposed before a controlled handover to operations.

D:

That action tackles a problem where premature closure lacks controlled preservation, handover and contractual accountability. The reported issue is instead that project closure is being proposed before a controlled handover to operations.

Question 774

For the documented project problem below, which outcome should be verified? A regional transport platform finishes implementation but the support team has not accepted ownership of ongoing incidents and service levels.

  1. The end project report and handover record identify each residual item and its owner.
  2. The board receives an acceptance record tied to the approved project product description.
  3. The service owner signs off operational readiness and responsibilities are recorded.
  4. The board decision rests on verified safety acceptance rather than a claimed task completion.

Explanation

Correct Answer

C:

Successful remediation is demonstrated when: The service owner signs off operational readiness and responsibilities are recorded. That result connects to the targeted action: Agree operational ownership, support information and transition acceptance before closure authorization. The previously observed defect was: Project closure is being proposed before a controlled handover to operations.

Incorrect Answers

A:

It would be evidence for a problem in which closing activities have not resolved or transferred remaining issues as actionable follow-on work. It does not verify that the service owner signs off operational readiness and responsibilities are recorded.

B:

That outcome could matter in a case where the closing project process has not confirmed acceptance of products against their criteria, but the present check needs to show that the service owner signs off operational readiness and responsibilities are recorded.

D:

The offered finding is relevant when the completion recommendation is inconsistent with the actual acceptance status of a critical product. Here the acceptance test must show that the service owner signs off operational readiness and responsibilities are recorded.

Question 775

Consider a PRINCE2 Project Management (Version 7) scenario: A regional transport platform finishes implementation but the support team has not accepted ownership of ongoing incidents and service levels. Which underlying management weakness most directly explains it?

  1. The closing process omits lessons reporting needed to improve future projects.
  2. The completion recommendation is inconsistent with the actual acceptance status of a critical product.
  3. Project closure is being confused with completion of all future benefit realization.
  4. Project closure is being proposed before a controlled handover to operations.

Explanation

Correct Answer

D:

This mechanism accounts for the observation: Project closure is being proposed before a controlled handover to operations. Address it by implementing: Agree operational ownership, support information and transition acceptance before closure authorization. Confirm the fix through: The service owner signs off operational readiness and responsibilities are recorded.

Incorrect Answers

A:

There could be such a cause if the closing process omits lessons reporting needed to improve future projects. The stated incident instead arises because project closure is being proposed before a controlled handover to operations.

B:

This diagnosis fits a situation in which the completion recommendation is inconsistent with the actual acceptance status of a critical product. Here, project closure is being proposed before a controlled handover to operations.

C:

The mechanism could explain a fault where project closure is being confused with completion of all future benefit realization; it does not account for the current condition, where project closure is being proposed before a controlled handover to operations.

Question 776

After dealing with this project failure—A regional transport platform finishes implementation but the support team has not accepted ownership of ongoing incidents and service levels.—which governance safeguard should be retained?

  1. Make final lesson reporting and organizational learning a closure requirement.
  2. Make operational handover and support acceptance closure prerequisites.
  3. Require baseline-versus-actual evidence for time, cost, quality, risk and sustainability at closure.
  4. Reconcile final-stage product status against acceptance records before closure.

Explanation

Correct Answer

B:

To prevent the same issue, apply this check: Make operational handover and support acceptance closure prerequisites. The risk to contain is: Project closure is being proposed before a controlled handover to operations. Verify control effectiveness using: The service owner signs off operational readiness and responsibilities are recorded.

Incorrect Answers

A:

The proposed routine targets situations in which the closing process omits lessons reporting needed to improve future projects. To prevent the reported problem, the team must address the fact that project closure is being proposed before a controlled handover to operations.

C:

This safeguard is useful when the closing report does not provide a reliable assessment of overall project performance. It does not prevent the present fault, where project closure is being proposed before a controlled handover to operations.

D:

This safeguard is useful when the completion recommendation is inconsistent with the actual acceptance status of a critical product. It does not prevent the present fault, where project closure is being proposed before a controlled handover to operations.

Question 777

During a Practitioner-level project review, the following has occurred: A wastewater sensor rollout has finished the final stage but numerous low-level issues remain without owners or follow-up dates. What should the accountable project role do next?

  1. Document outstanding issues and agree accountable follow-on actions with the receiving business owners.
  2. Obtain authorized user acceptance or formally resolve deficiencies before recommending closure.
  3. Complete or formally resolve the inspection and update the end project report before seeking closure.
  4. Use the closing process in a tailored premature-closure form to document products, costs, obligations and lessons.

Explanation

Correct Answer

A:

Choose this fix: Document outstanding issues and agree accountable follow-on actions with the receiving business owners. It repairs the stated issue, where Closing activities have not resolved or transferred remaining issues as actionable follow-on work. The result should be independently established through: The end project report and handover record identify each residual item and its owner.

Incorrect Answers

B:

When the closing project process has not confirmed acceptance of products against their criteria, “Obtain authorized user acceptance or formally resolve deficiencies before recommending closure” could be justified. Here, closing activities have not resolved or transferred remaining issues as actionable follow-on work, so this is not the needed correction.

C:

When the completion recommendation is inconsistent with the actual acceptance status of a critical product, “Complete or formally resolve the inspection and update the end project report before seeking closure” could be justified. Here, closing activities have not resolved or transferred remaining issues as actionable follow-on work, so this is not the needed correction.

D:

That action tackles a problem where premature closure lacks controlled preservation, handover and contractual accountability. The reported issue is instead that closing activities have not resolved or transferred remaining issues as actionable follow-on work.

Question 778

A project assurance reviewer validates a response to this scenario: A wastewater sensor rollout has finished the final stage but numerous low-level issues remain without owners or follow-up dates. What finding supports closure?

  1. The board closes delivery with a documented post-project benefits review schedule and accountable senior user.
  2. The board decision rests on verified safety acceptance rather than a claimed task completion.
  3. The service owner signs off operational readiness and responsibilities are recorded.
  4. The end project report and handover record identify each residual item and its owner.

Explanation

Correct Answer

D:

The strongest confirmation is: The end project report and handover record identify each residual item and its owner. It is evidence for the specific corrective step—Document outstanding issues and agree accountable follow-on actions with the receiving business owners.—rather than a generic system-health signal.

Incorrect Answers

A:

That outcome could matter in a case where project closure is being confused with completion of all future benefit realization, but the present check needs to show that the end project report and handover record identify each residual item and its owner.

B:

That outcome could matter in a case where the completion recommendation is inconsistent with the actual acceptance status of a critical product, but the present check needs to show that the end project report and handover record identify each residual item and its owner.

C:

That outcome could matter in a case where project closure is being proposed before a controlled handover to operations, but the present check needs to show that the end project report and handover record identify each residual item and its owner.

Question 779

In this project situation, A wastewater sensor rollout has finished the final stage but numerous low-level issues remain without owners or follow-up dates. What weakness should be corrected?

  1. Closing activities have not resolved or transferred remaining issues as actionable follow-on work.
  2. The closing project process has not confirmed acceptance of products against their criteria.
  3. The closing report does not provide a reliable assessment of overall project performance.
  4. Project closure is being confused with completion of all future benefit realization.

Explanation

Correct Answer

A:

The failure is explained by: Closing activities have not resolved or transferred remaining issues as actionable follow-on work. It supports the targeted intervention: Document outstanding issues and agree accountable follow-on actions with the receiving business owners. The observable test of success is: The end project report and handover record identify each residual item and its owner.

Incorrect Answers

B:

The mechanism could explain a fault where the closing project process has not confirmed acceptance of products against their criteria; it does not account for the current condition, where closing activities have not resolved or transferred remaining issues as actionable follow-on work.

C:

The cause in this option would matter if the closing report does not provide a reliable assessment of overall project performance. The reported failure instead arises because closing activities have not resolved or transferred remaining issues as actionable follow-on work.

D:

The mechanism could explain a fault where project closure is being confused with completion of all future benefit realization; it does not account for the current condition, where closing activities have not resolved or transferred remaining issues as actionable follow-on work.

Question 780

A Practitioner recommends a permanent improvement after this problem: A wastewater sensor rollout has finished the final stage but numerous low-level issues remain without owners or follow-up dates. Which control is most effective?

  1. Reconcile final-stage product status against acceptance records before closure.
  2. Include a viable post-project benefits review arrangement in closure artifacts.
  3. Apply proportionate controlled closure steps even when a project is stopped early.
  4. Require residual issue disposition and handover ownership before board closure.

Explanation

Correct Answer

D:

This practice reduces the documented recurrence risk: Require residual issue disposition and handover ownership before board closure. The original root fault was: Closing activities have not resolved or transferred remaining issues as actionable follow-on work. The practical health indicator is: The end project report and handover record identify each residual item and its owner.

Incorrect Answers

A:

The control would be appropriate if the completion recommendation is inconsistent with the actual acceptance status of a critical product; the issue here is that closing activities have not resolved or transferred remaining issues as actionable follow-on work.

B:

The control would be appropriate if project closure is being confused with completion of all future benefit realization; the issue here is that closing activities have not resolved or transferred remaining issues as actionable follow-on work.

C:

This safeguard is useful when premature closure lacks controlled preservation, handover and contractual accountability. It does not prevent the present fault, where closing activities have not resolved or transferred remaining issues as actionable follow-on work.