Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 79

Question 780

A Practitioner recommends a permanent improvement after this problem: A wastewater sensor rollout has finished the final stage but numerous low-level issues remain without owners or follow-up dates. Which control is most effective?

  1. Reconcile final-stage product status against acceptance records before closure.
  2. Include a viable post-project benefits review arrangement in closure artifacts.
  3. Apply proportionate controlled closure steps even when a project is stopped early.
  4. Require residual issue disposition and handover ownership before board closure.

Explanation

Correct Answer

D:

This practice reduces the documented recurrence risk: Require residual issue disposition and handover ownership before board closure. The original root fault was: Closing activities have not resolved or transferred remaining issues as actionable follow-on work. The practical health indicator is: The end project report and handover record identify each residual item and its owner.

Incorrect Answers

A:

The control would be appropriate if the completion recommendation is inconsistent with the actual acceptance status of a critical product; the issue here is that closing activities have not resolved or transferred remaining issues as actionable follow-on work.

B:

The control would be appropriate if project closure is being confused with completion of all future benefit realization; the issue here is that closing activities have not resolved or transferred remaining issues as actionable follow-on work.

C:

This safeguard is useful when premature closure lacks controlled preservation, handover and contractual accountability. It does not prevent the present fault, where closing activities have not resolved or transferred remaining issues as actionable follow-on work.

Question 781

A project board member examines the following problem: A public schools connectivity project ends under budget and the manager discards its lessons log instead of reporting experience. Which proposed next step best fits PRINCE2?

  1. Prepare the end project report with actual performance against the authorized baselines and outstanding benefit actions.
  2. Obtain authorized user acceptance or formally resolve deficiencies before recommending closure.
  3. Use the closing process in a tailored premature-closure form to document products, costs, obligations and lessons.
  4. Prepare a lessons report identifying what worked and what should change and share with the appropriate organization.

Explanation

Correct Answer

D:

Prepare a lessons report identifying what worked and what should change and share with the appropriate organization. This is the appropriate intervention because the closing process omits lessons reporting needed to improve future projects. The specific outcome to verify is: The lessons report is accepted and relevant improvement owners are named.

Incorrect Answers

A:

The option would help when the closing report does not provide a reliable assessment of overall project performance, but it would not address a situation where the closing process omits lessons reporting needed to improve future projects.

B:

When the closing project process has not confirmed acceptance of products against their criteria, “Obtain authorized user acceptance or formally resolve deficiencies before recommending closure” could be justified. Here, the closing process omits lessons reporting needed to improve future projects, so this is not the needed correction.

C:

That action tackles a problem where premature closure lacks controlled preservation, handover and contractual accountability. The reported issue is instead that the closing process omits lessons reporting needed to improve future projects.

Question 782

Which result best demonstrates appropriate PRINCE2 application in this situation? A public schools connectivity project ends under budget and the manager discards its lessons log instead of reporting experience.

  1. The board closes delivery with a documented post-project benefits review schedule and accountable senior user.
  2. The board decision rests on verified safety acceptance rather than a claimed task completion.
  3. The end project report and handover record identify each residual item and its owner.
  4. The lessons report is accepted and relevant improvement owners are named.

Explanation

Correct Answer

D:

This finding directly demonstrates the intended result: The lessons report is accepted and relevant improvement owners are named. It tests whether the chosen remediation—Prepare a lessons report identifying what worked and what should change and share with the appropriate organization.—has addressed the cause: The closing process omits lessons reporting needed to improve future projects.

Incorrect Answers

A:

The observation relates to a problem where project closure is being confused with completion of all future benefit realization; the required finding here is that the lessons report is accepted and relevant improvement owners are named.

B:

The offered finding is relevant when the completion recommendation is inconsistent with the actual acceptance status of a critical product. Here the acceptance test must show that the lessons report is accepted and relevant improvement owners are named.

C:

The observation relates to a problem where closing activities have not resolved or transferred remaining issues as actionable follow-on work; the required finding here is that the lessons report is accepted and relevant improvement owners are named.

Question 783

The following problem has arisen during a project: A public schools connectivity project ends under budget and the manager discards its lessons log instead of reporting experience. Which cause fits the evidence?

  1. Project closure is being proposed before a controlled handover to operations.
  2. The completion recommendation is inconsistent with the actual acceptance status of a critical product.
  3. The closing process omits lessons reporting needed to improve future projects.
  4. Closing activities have not resolved or transferred remaining issues as actionable follow-on work.

Explanation

Correct Answer

C:

The identified root cause is: The closing process omits lessons reporting needed to improve future projects. The appropriate correction is: Prepare a lessons report identifying what worked and what should change and share with the appropriate organization. A separate validation must then show: The lessons report is accepted and relevant improvement owners are named.

Incorrect Answers

A:

This diagnosis fits a situation in which project closure is being proposed before a controlled handover to operations. Here, the closing process omits lessons reporting needed to improve future projects.

B:

The proposed diagnosis concerns a problem where the completion recommendation is inconsistent with the actual acceptance status of a critical product. The facts here indicate that the closing process omits lessons reporting needed to improve future projects.

D:

The mechanism could explain a fault where closing activities have not resolved or transferred remaining issues as actionable follow-on work; it does not account for the current condition, where the closing process omits lessons reporting needed to improve future projects.

Question 784

What recurring PRINCE2 control would best prevent this situation from happening again? A public schools connectivity project ends under budget and the manager discards its lessons log instead of reporting experience.

  1. Include signed user acceptance in the closing-project checklist.
  2. Make final lesson reporting and organizational learning a closure requirement.
  3. Reconcile final-stage product status against acceptance records before closure.
  4. Apply proportionate controlled closure steps even when a project is stopped early.

Explanation

Correct Answer

B:

The lasting control is: Make final lesson reporting and organizational learning a closure requirement. It addresses recurrence of this mechanism: The closing process omits lessons reporting needed to improve future projects. A successful system should still demonstrate: The lessons report is accepted and relevant improvement owners are named.

Incorrect Answers

A:

The option addresses cases in which the closing project process has not confirmed acceptance of products against their criteria. In the reported incident, the closing process omits lessons reporting needed to improve future projects instead.

C:

The control would be appropriate if the completion recommendation is inconsistent with the actual acceptance status of a critical product; the issue here is that the closing process omits lessons reporting needed to improve future projects.

D:

The option addresses cases in which premature closure lacks controlled preservation, handover and contractual accountability. In the reported incident, the closing process omits lessons reporting needed to improve future projects instead.

Question 785

A PRINCE2 Project Management (Version 7) team faces this situation: A hospital analytics project delivers the dashboard but the expected clinical outcome can only be measured six months after handover. Which corrective governance or delivery action is most appropriate?

  1. Obtain authorized user acceptance or formally resolve deficiencies before recommending closure.
  2. Prepare a lessons report identifying what worked and what should change and share with the appropriate organization.
  3. Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization.
  4. Document outstanding issues and agree accountable follow-on actions with the receiving business owners.

Explanation

Correct Answer

C:

The case requires this change: Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization. The actual failure mechanism is: Project closure is being confused with completion of all future benefit realization. A meaningful acceptance check is: The board closes delivery with a documented post-project benefits review schedule and accountable senior user.

Incorrect Answers

A:

This change addresses a situation in which the closing project process has not confirmed acceptance of products against their criteria. It leaves the current failure unresolved because project closure is being confused with completion of all future benefit realization.

B:

When the closing process omits lessons reporting needed to improve future projects, “Prepare a lessons report identifying what worked and what should change and share with the appropriate organization” could be justified. Here, project closure is being confused with completion of all future benefit realization, so this is not the needed correction.

D:

When closing activities have not resolved or transferred remaining issues as actionable follow-on work, “Document outstanding issues and agree accountable follow-on actions with the receiving business owners” could be justified. Here, project closure is being confused with completion of all future benefit realization, so this is not the needed correction.

Question 786

The project team reports that it resolved the following issue: A hospital analytics project delivers the dashboard but the expected clinical outcome can only be measured six months after handover. Which observed result is the best acceptance evidence?

  1. The board decision rests on verified safety acceptance rather than a claimed task completion.
  2. The board receives an acceptance record tied to the approved project product description.
  3. The lessons report is accepted and relevant improvement owners are named.
  4. The board closes delivery with a documented post-project benefits review schedule and accountable senior user.

Explanation

Correct Answer

D:

Successful remediation is demonstrated when: The board closes delivery with a documented post-project benefits review schedule and accountable senior user. That result connects to the targeted action: Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization. The previously observed defect was: Project closure is being confused with completion of all future benefit realization.

Incorrect Answers

A:

It would be evidence for a problem in which the completion recommendation is inconsistent with the actual acceptance status of a critical product. It does not verify that the board closes delivery with a documented post-project benefits review schedule and accountable senior user.

B:

This result could confirm a fix when the closing project process has not confirmed acceptance of products against their criteria. It would not demonstrate that the board closes delivery with a documented post-project benefits review schedule and accountable senior user.

C:

It would be evidence for a problem in which the closing process omits lessons reporting needed to improve future projects. It does not verify that the board closes delivery with a documented post-project benefits review schedule and accountable senior user.

Question 787

A Practitioner exam candidate analyses: A hospital analytics project delivers the dashboard but the expected clinical outcome can only be measured six months after handover. Which diagnosis best accounts for the observed governance failure?

  1. Premature closure lacks controlled preservation, handover and contractual accountability.
  2. The completion recommendation is inconsistent with the actual acceptance status of a critical product.
  3. Closing activities have not resolved or transferred remaining issues as actionable follow-on work.
  4. Project closure is being confused with completion of all future benefit realization.

Explanation

Correct Answer

D:

This mechanism accounts for the observation: Project closure is being confused with completion of all future benefit realization. Address it by implementing: Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization. Confirm the fix through: The board closes delivery with a documented post-project benefits review schedule and accountable senior user.

Incorrect Answers

A:

The cause in this option would matter if premature closure lacks controlled preservation, handover and contractual accountability. The reported failure instead arises because project closure is being confused with completion of all future benefit realization.

B:

The proposed diagnosis concerns a problem where the completion recommendation is inconsistent with the actual acceptance status of a critical product. The facts here indicate that project closure is being confused with completion of all future benefit realization.

C:

This diagnosis fits a situation in which closing activities have not resolved or transferred remaining issues as actionable follow-on work. Here, project closure is being confused with completion of all future benefit realization.

Question 788

Which ongoing review or control is most appropriate for avoiding a repeat of the following project incident? A hospital analytics project delivers the dashboard but the expected clinical outcome can only be measured six months after handover.

  1. Apply proportionate controlled closure steps even when a project is stopped early.
  2. Make final lesson reporting and organizational learning a closure requirement.
  3. Require residual issue disposition and handover ownership before board closure.
  4. Include a viable post-project benefits review arrangement in closure artifacts.

Explanation

Correct Answer

D:

To prevent the same issue, apply this check: Include a viable post-project benefits review arrangement in closure artifacts. The risk to contain is: Project closure is being confused with completion of all future benefit realization. Verify control effectiveness using: The board closes delivery with a documented post-project benefits review schedule and accountable senior user.

Incorrect Answers

A:

The control would be appropriate if premature closure lacks controlled preservation, handover and contractual accountability; the issue here is that project closure is being confused with completion of all future benefit realization.

B:

This safeguard is useful when the closing process omits lessons reporting needed to improve future projects. It does not prevent the present fault, where project closure is being confused with completion of all future benefit realization.

C:

The option addresses cases in which closing activities have not resolved or transferred remaining issues as actionable follow-on work. In the reported incident, project closure is being confused with completion of all future benefit realization instead.

Question 789

A project manager is assessing this situation: A park renovation project manager asks the project board to close the project while the final stage plan still lists an unaccepted safety inspection. What action would restore appropriate control?

  1. Document outstanding issues and agree accountable follow-on actions with the receiving business owners.
  2. Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization.
  3. Prepare a lessons report identifying what worked and what should change and share with the appropriate organization.
  4. Complete or formally resolve the inspection and update the end project report before seeking closure.

Explanation

Correct Answer

D:

Choose this fix: Complete or formally resolve the inspection and update the end project report before seeking closure. It repairs the stated issue, where the completion recommendation is inconsistent with the actual acceptance status of a critical product. The result should be independently established through: The board decision rests on verified safety acceptance rather than a claimed task completion.

Incorrect Answers

A:

This change addresses a situation in which closing activities have not resolved or transferred remaining issues as actionable follow-on work. It leaves the current failure unresolved because the completion recommendation is inconsistent with the actual acceptance status of a critical product.

B:

When project closure is being confused with completion of all future benefit realization, “Finalize benefit measures, owners and review dates and transfer monitoring to the operating organization” could be justified. Here, the completion recommendation is inconsistent with the actual acceptance status of a critical product, so this is not the needed correction.

C:

When the closing process omits lessons reporting needed to improve future projects, “Prepare a lessons report identifying what worked and what should change and share with the appropriate organization” could be justified. Here, the completion recommendation is inconsistent with the actual acceptance status of a critical product, so this is not the needed correction.

Question 790

The board requests proof that this project fault is controlled: A park renovation project manager asks the project board to close the project while the final stage plan still lists an unaccepted safety inspection. Which result is most relevant?

  1. The lessons report is accepted and relevant improvement owners are named.
  2. The board decision rests on verified safety acceptance rather than a claimed task completion.
  3. The service owner signs off operational readiness and responsibilities are recorded.
  4. The end project report and handover record identify each residual item and its owner.

Explanation

Correct Answer

B:

The strongest confirmation is: The board decision rests on verified safety acceptance rather than a claimed task completion. It is evidence for the specific corrective step—Complete or formally resolve the inspection and update the end project report before seeking closure.—rather than a generic system-health signal.

Incorrect Answers

A:

The observation relates to a problem where the closing process omits lessons reporting needed to improve future projects; the required finding here is that the board decision rests on verified safety acceptance rather than a claimed task completion.

C:

The offered finding is relevant when project closure is being proposed before a controlled handover to operations. Here the acceptance test must show that the board decision rests on verified safety acceptance rather than a claimed task completion.

D:

This result could confirm a fix when closing activities have not resolved or transferred remaining issues as actionable follow-on work. It would not demonstrate that the board decision rests on verified safety acceptance rather than a claimed task completion.

PRINCE2 7 Practitioner Practice Tests