Question 750
A project assurance reviewer validates a response to this scenario: A research infrastructure project has completed an initiation stage but has no detailed plan for its first delivery stage. What finding supports closure?
Explanation
Correct Answer
Successful remediation is demonstrated when: The board can make a separate informed decision on the first delivery stage after project authorization. That result connects to the targeted action: Use managing a stage boundary after initiation to assemble the first delivery stage plan for board approval. The previously observed defect was: The initiation-to-delivery transition lacks stage boundary planning for the next authorization.
Incorrect Answers
The observation relates to a problem where next-stage planning is disconnected from a material supplier change; the required finding here is that the board can make a separate informed decision on the first delivery stage after project authorization.
That outcome could matter in a case where managing a stage boundary has been bypassed before requesting the next authorization, but the present check needs to show that the board can make a separate informed decision on the first delivery stage after project authorization.
The offered finding is relevant when stage boundary activities have not applied lessons to the forthcoming stage plan. Here the acceptance test must show that the board can make a separate informed decision on the first delivery stage after project authorization.