Question 70
Following the proposed correction, what observation confirms success: An agile team freezes business analysis until a six-month requirements document is signed, delaying feedback from early increments.
Explanation
Correct Answer
Each increment has current accepted requirements with feedback incorporated. This validates the selected response: Conduct just-in-time requirements refinement and stakeholder validation alongside iterative delivery. The relevant management principle is: Adaptive BA is ongoing and supports evolving backlog decisions.
Incorrect Answers
Stakeholders can see current priorities without treating all future ideas as fixed scope. This is evidence for ANOTHER case: A business analyst promotes every proposed backlog item to scope baseline in an agile product, preventing legitimate reprioritization. The specific corrective response here is: Conduct just-in-time requirements refinement and stakeholder validation alongside iterative delivery.
Regulatory and contractual requirements are approved before dependent procurement. This is evidence for ANOTHER case: A predictive construction contract begins without any approved requirements baseline because the BA assumes stories will change every sprint. The specific corrective response here is: Conduct just-in-time requirements refinement and stakeholder validation alongside iterative delivery.
Unresolved acceptance conflicts reach accountable business governance with delivery impact analysis. This is evidence for ANOTHER case: A team treats a business sponsor and the delivery PM as interchangeable when resolving conflicting product acceptance goals. The specific corrective response here is: Conduct just-in-time requirements refinement and stakeholder validation alongside iterative delivery.