Question 50
The project issue was: An agile team marks a story done because coding finished even though its required customer acceptance test failed. Which outcome demonstrates that its remedy worked?
Explanation
Correct Answer
The story passes authorized functional tests and is accepted. This validates the selected response: Complete the agreed acceptance criteria and definition of done before counting the story delivered. The relevant management principle is: A completed task must satisfy accepted outcome criteria, not just coding effort.
Incorrect Answers
Throughput metrics align with completed user value and actual acceptance evidence. This is evidence for ANOTHER case: A team repeatedly splits stories after sprint completion to make velocity reports look favorable. The specific corrective response here is: Complete the agreed acceptance criteria and definition of done before counting the story delivered.
The test scenario proves whether the story fulfills the requested behavior. This is evidence for ANOTHER case: A team starts implementation from a vague user story with no expected behavior or acceptance criteria. The specific corrective response here is: Complete the agreed acceptance criteria and definition of done before counting the story delivered.
Cycle time and work-in-progress decrease while throughput stabilizes. This is evidence for ANOTHER case: A Kanban team does not display work-in-progress limits and has 25 concurrent tasks, none finished. The specific corrective response here is: Complete the agreed acceptance criteria and definition of done before counting the story delivered.