McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 10

Question 90

How should the project team verify a successful response to: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient.

  1. The benefit report compares before-and-after time with the agreed target.
  2. The mitigation has an assigned owner and funded schedule activities.
  3. Independent evaluation records document a fair, reviewable procurement decision.
  4. The sponsor receives timely, accurate escalation and options.

Explanation

Correct Answer

D:

The sponsor receives timely, accurate escalation and options. This validates the selected response: Follow the agreed communication and escalation plan with verified variance evidence. The relevant management principle is: Communication strategies define who needs which information and when.

Incorrect Answers

A:

The benefit report compares before-and-after time with the agreed target. This is evidence for ANOTHER case: A product experiment delivers a feature but does not measure whether customer service time actually improved. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.

B:

The mitigation has an assigned owner and funded schedule activities. This is evidence for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.

C:

Independent evaluation records document a fair, reviewable procurement decision. This is evidence for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.

Question 91

A project team asks why this occurs: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. Which project management principle best explains it?

  1. Communication strategies define who needs which information and when.
  2. Communication strategy includes appropriate confidentiality and audience selection.
  3. Without a benchmark, claiming realized change is not testable.
  4. Portfolios optimize strategic investments and need not comprise mutually dependent projects.

Explanation

Correct Answer

A:

Communication strategies define who needs which information and when. This explains the case: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. The targeted action is: Follow the agreed communication and escalation plan with verified variance evidence.

Incorrect Answers

B:

Communication strategy includes appropriate confidentiality and audience selection. This rationale better explains a DIFFERENT problem: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution. The key mechanism for the current situation is: Communication strategies define who needs which information and when.

C:

Without a benchmark, claiming realized change is not testable. This rationale better explains a DIFFERENT problem: A project initiation memo promises growth but includes no baseline of current performance. The key mechanism for the current situation is: Communication strategies define who needs which information and when.

D:

Portfolios optimize strategic investments and need not comprise mutually dependent projects. This rationale better explains a DIFFERENT problem: A university investment committee labels its unrelated campus construction and digital learning initiatives a single program. The key mechanism for the current situation is: Communication strategies define who needs which information and when.

Question 92

At a small product delivery team, the team wants to avoid repeating: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. Which safeguard should it retain?

  1. Trace material response plans to the budget baseline.
  2. Audit critical communication triggers during governance reviews.
  3. Revisit value alignment at phase reviews.
  4. Assign postdelivery benefits accountability at authorization.

Explanation

Correct Answer

B:

Audit critical communication triggers during governance reviews. This helps prevent recurrence of: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. The required evidence of effective control is: The sponsor receives timely, accurate escalation and options.

Incorrect Answers

A:

Trace material response plans to the budget baseline. That is a useful control for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The current situation is better prevented by: Audit critical communication triggers during governance reviews.

C:

Revisit value alignment at phase reviews. That is a useful control for ANOTHER case: A sponsor approved a high-level benefit target, but the project team starts building unrelated features because no value owner is identified. The current situation is better prevented by: Audit critical communication triggers during governance reviews.

D:

Assign postdelivery benefits accountability at authorization. That is a useful control for ANOTHER case: A product launch team attributes declining customer churn to its project but has defined no measurable benefit baseline. The current situation is better prevented by: Audit critical communication triggers during governance reviews.

Question 93

A CAPM-level project coordinator sees: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead. What is the best next approved step?

  1. Separate an initial divergence session from later feasibility evaluation.
  2. Apply a blameless cause analysis using defect patterns and process controls.
  3. Store controlled versions of approved planning artifacts with change histories.
  4. Facilitate a focused user group with relevant participants and open-ended questions.

Explanation

Correct Answer

D:

Facilitate a focused user group with relevant participants and open-ended questions. This addresses the fictional case: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead. The project-management rationale is: Focus groups elicit qualitative perspectives better than one-way executive reporting. Verify by: The team captures diverse usability observations and themes.

Incorrect Answers

A:

Separate an initial divergence session from later feasibility evaluation. This would address a DIFFERENT fictional project situation: An innovation workshop spends all its time assessing budgets and never generates alternative approaches. It is less directly applicable to: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead.

B:

Apply a blameless cause analysis using defect patterns and process controls. This would address a DIFFERENT fictional project situation: A retrospective blames one employee for recurring defect escapes without reviewing workflow causes. It is less directly applicable to: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead.

C:

Store controlled versions of approved planning artifacts with change histories. This would address a DIFFERENT fictional project situation: A public-sector project tracks decisions only in hallway conversations and cannot locate baseline approvals. It is less directly applicable to: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead.

Question 94

For an engineering consulting project, what is the strongest acceptance evidence after addressing: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead.

  1. The team captures diverse usability observations and themes.
  2. Participants receive documented outcomes and responsible owners.
  3. The final decision reflects verified operational constraints and authority.
  4. The risk register contains uncertain event descriptions, owners and responses.

Explanation

Correct Answer

A:

The team captures diverse usability observations and themes. This validates the selected response: Facilitate a focused user group with relevant participants and open-ended questions. The relevant management principle is: Focus groups elicit qualitative perspectives better than one-way executive reporting.

Incorrect Answers

B:

Participants receive documented outcomes and responsible owners. This is evidence for ANOTHER case: An online workshop invites forty participants but never records decisions or follow-up tasks. The specific corrective response here is: Facilitate a focused user group with relevant participants and open-ended questions.

C:

The final decision reflects verified operational constraints and authority. This is evidence for ANOTHER case: A stakeholder workshop repeatedly includes decision makers who do not understand the topic but excludes the operators doing the work. The specific corrective response here is: Facilitate a focused user group with relevant participants and open-ended questions.

D:

The risk register contains uncertain event descriptions, owners and responses. This is evidence for ANOTHER case: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The specific corrective response here is: Facilitate a focused user group with relevant participants and open-ended questions.

Question 95

A postincident review considers: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead. Which principle most directly accounts for the behavior?

  1. Brainstorming is for generating alternatives before critical selection.
  2. Focus groups elicit qualitative perspectives better than one-way executive reporting.
  3. Meeting effectiveness depends on useful outcomes rather than attendance alone.
  4. Adaptive approaches accommodate evolving requirements where detailed predictive baselines are unstable.

Explanation

Correct Answer

B:

Focus groups elicit qualitative perspectives better than one-way executive reporting. This explains the case: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead. The targeted action is: Facilitate a focused user group with relevant participants and open-ended questions.

Incorrect Answers

A:

Brainstorming is for generating alternatives before critical selection. This rationale better explains a DIFFERENT problem: An innovation workshop spends all its time assessing budgets and never generates alternative approaches. The key mechanism for the current situation is: Focus groups elicit qualitative perspectives better than one-way executive reporting.

C:

Meeting effectiveness depends on useful outcomes rather than attendance alone. This rationale better explains a DIFFERENT problem: A project meeting repeatedly exceeds an hour with no agenda or decision owner and produces no actions. The key mechanism for the current situation is: Focus groups elicit qualitative perspectives better than one-way executive reporting.

D:

Adaptive approaches accommodate evolving requirements where detailed predictive baselines are unstable. This rationale better explains a DIFFERENT problem: A manufacturing team freezes all product details up front despite weekly regulatory discoveries that regularly change requirements. The key mechanism for the current situation is: Focus groups elicit qualitative perspectives better than one-way executive reporting.

Question 96

What ongoing preventive practice would most reduce recurrence of: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead.

  1. Review recurring meeting outcomes and cancel low-value sessions.
  2. Include follow-up reconciliation in facilitation checklists.
  3. Choose research techniques by information need.
  4. Ask teams for recurring impediment feedback.

Explanation

Correct Answer

C:

Choose research techniques by information need. This helps prevent recurrence of: A clinic wants candid feedback on new appointment kiosks but managers conduct a public executive presentation instead. The required evidence of effective control is: The team captures diverse usability observations and themes.

Incorrect Answers

A:

Review recurring meeting outcomes and cancel low-value sessions. That is a useful control for ANOTHER case: A project meeting repeatedly exceeds an hour with no agenda or decision owner and produces no actions. The current situation is better prevented by: Choose research techniques by information need.

B:

Include follow-up reconciliation in facilitation checklists. That is a useful control for ANOTHER case: An online workshop invites forty participants but never records decisions or follow-up tasks. The current situation is better prevented by: Choose research techniques by information need.

D:

Ask teams for recurring impediment feedback. That is a useful control for ANOTHER case: An agile facilitator evaluates team success by how many direct orders team members obey. The current situation is better prevented by: Choose research techniques by information need.

Question 97

At a nonprofit modernization team, the review identifies: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. Which response best addresses the specific project management problem?

  1. Clarify resource authority with functional managers and the project manager in the project governance plan.
  2. Use a predictive lifecycle with controlled baseline and compliance checkpoints for stable requirements.
  3. Negotiate a documented allocation and escalation path consistent with the organizational structure.
  4. Calculate schedule variance as EV minus PV and report the negative $10,000 value.

Explanation

Correct Answer

A:

Clarify resource authority with functional managers and the project manager in the project governance plan. This addresses the fictional case: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. The project-management rationale is: Matrix structures distribute authority between project and functional management. Verify by: The specialist has one approved allocation during the test window.

Incorrect Answers

B:

Use a predictive lifecycle with controlled baseline and compliance checkpoints for stable requirements. This would address a DIFFERENT fictional project situation: A power-station upgrade has fixed regulatory specifications but a team proposes changing foundational requirements every week. It is less directly applicable to: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority.

C:

Negotiate a documented allocation and escalation path consistent with the organizational structure. This would address a DIFFERENT fictional project situation: A functional department loans staff to a project without acknowledging the project's fixed schedule responsibilities. It is less directly applicable to: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority.

D:

Calculate schedule variance as EV minus PV and report the negative $10,000 value. This would address a DIFFERENT fictional project situation: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. It is less directly applicable to: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority.

Question 98

The project issue was: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. Which outcome demonstrates that its remedy worked?

  1. A reviewable schedule links procurement, installation and inspection in the required order.
  2. The specialist has one approved allocation during the test window.
  3. The work breakdown shows migration outputs and operating handoff without claiming indefinite support as project work.
  4. Suppliers acknowledge a single approved milestone baseline.

Explanation

Correct Answer

B:

The specialist has one approved allocation during the test window. This validates the selected response: Clarify resource authority with functional managers and the project manager in the project governance plan. The relevant management principle is: Matrix structures distribute authority between project and functional management.

Incorrect Answers

A:

A reviewable schedule links procurement, installation and inspection in the required order. This is evidence for ANOTHER case: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. The specific corrective response here is: Clarify resource authority with functional managers and the project manager in the project governance plan.

C:

The work breakdown shows migration outputs and operating handoff without claiming indefinite support as project work. This is evidence for ANOTHER case: A planning coordinator includes routine daily customer support as the completion deliverable for a time-limited database migration. The specific corrective response here is: Clarify resource authority with functional managers and the project manager in the project governance plan.

D:

Suppliers acknowledge a single approved milestone baseline. This is evidence for ANOTHER case: A government project holds a scope baseline but shares no signed schedule version with its suppliers. The specific corrective response here is: Clarify resource authority with functional managers and the project manager in the project governance plan.

Question 99

For a nonprofit modernization team, the documented failure was: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. Which explanation is most accurate?

  1. Predictive work spans multiple coordinated management processes, not task listing alone.
  2. Distinct project components require coordinated but identifiable responsibilities.
  3. Matrix structures distribute authority between project and functional management.
  4. Predictive variance must compare against legitimate current baselines.

Explanation

Correct Answer

C:

Matrix structures distribute authority between project and functional management. This explains the case: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. The targeted action is: Clarify resource authority with functional managers and the project manager in the project governance plan.

Incorrect Answers

A:

Predictive work spans multiple coordinated management processes, not task listing alone. This rationale better explains a DIFFERENT problem: A predictive project owner marks planning complete after listing tasks without defining expected integration, validation or closure activities. The key mechanism for the current situation is: Matrix structures distribute authority between project and functional management.

B:

Distinct project components require coordinated but identifiable responsibilities. This rationale better explains a DIFFERENT problem: A project lists stakeholder acceptance and maintenance training as tasks inside design engineering without distinct owners. The key mechanism for the current situation is: Matrix structures distribute authority between project and functional management.

D:

Predictive variance must compare against legitimate current baselines. This rationale better explains a DIFFERENT problem: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The key mechanism for the current situation is: Matrix structures distribute authority between project and functional management.

Question 100

Which recurring governance check best addresses the risk of repeating: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority.

  1. Check approval prerequisites in dependency reviews.
  2. Use a component checklist during plan development.
  3. Use clearly labeled baseline and forecast columns.
  4. Confirm decision rights for shared resources at initiation.

Explanation

Correct Answer

D:

Confirm decision rights for shared resources at initiation. This helps prevent recurrence of: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. The required evidence of effective control is: The specialist has one approved allocation during the test window.

Incorrect Answers

A:

Check approval prerequisites in dependency reviews. That is a useful control for ANOTHER case: A transit modernization project combines commissioning tests and public activation into one work package despite mandatory test signoff. The current situation is better prevented by: Confirm decision rights for shared resources at initiation.

B:

Use a component checklist during plan development. That is a useful control for ANOTHER case: A project lists stakeholder acceptance and maintenance training as tasks inside design engineering without distinct owners. The current situation is better prevented by: Confirm decision rights for shared resources at initiation.

C:

Use clearly labeled baseline and forecast columns. That is a useful control for ANOTHER case: A schedule control board receives a late delivery forecast but the project report fails to distinguish a revised forecast from approved baseline. The current situation is better prevented by: Confirm decision rights for shared resources at initiation.