  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 9

Question 80

What ongoing preventive practice would most reduce recurrence of: Three clinic software migrations share one coordinated benefit but have been managed as unrelated portfolios.

  1. Add license checks to acceptance for reused assets.
  2. Require conflicts to be disclosed before sourcing work.
  3. Test program proposals for shared dependencies and outcome ownership.
  4. Train contributors on register classification and fields.

Explanation

Correct Answer

C:

Test program proposals for shared dependencies and outcome ownership. This helps prevent recurrence of: Three clinic software migrations share one coordinated benefit but have been managed as unrelated portfolios. The required evidence of effective control is: Dependency and benefit reports span the three related projects rather than just ranking investments.

Incorrect Answers

A:

Add license checks to acceptance for reused assets. That is a useful control for ANOTHER case: Two internal departments dispute a licensed design and one party proposes using the material without consent. The current situation is better prevented by: Test program proposals for shared dependencies and outcome ownership.

B:

Require conflicts to be disclosed before sourcing work. That is a useful control for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The current situation is better prevented by: Test program proposals for shared dependencies and outcome ownership.

D:

Train contributors on register classification and fields. That is a useful control for ANOTHER case: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The current situation is better prevented by: Test program proposals for shared dependencies and outcome ownership.

Question 81

At a manufacturing equipment project, the review identifies: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. Which response best addresses the specific project management problem?

  1. Distinguish product direction from the project's execution, control and delivery baselines.
  2. Record relevant stakeholder roles, interests, influence and planned engagement.
  3. Define testable deliverable acceptance criteria with the customer before delivery.
  4. Establish a program that coordinates dependent migrations and shared benefits under the parent objective.

Explanation

Correct Answer

A:

Distinguish product direction from the project's execution, control and delivery baselines. This addresses the fictional case: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The project-management rationale is: Product plans describe evolving product direction while project plans govern a specific undertaking. Verify by: Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist.

Incorrect Answers

B:

Record relevant stakeholder roles, interests, influence and planned engagement. This would address a DIFFERENT fictional project situation: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. It is less directly applicable to: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan.

C:

Define testable deliverable acceptance criteria with the customer before delivery. This would address a DIFFERENT fictional project situation: A project team approves a feature list but has no measurable criterion for accepting the final release. It is less directly applicable to: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan.

D:

Establish a program that coordinates dependent migrations and shared benefits under the parent objective. This would address a DIFFERENT fictional project situation: Three clinic software migrations share one coordinated benefit but have been managed as unrelated portfolios. It is less directly applicable to: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan.

Question 82

The project issue was: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. Which outcome demonstrates that its remedy worked?

  1. The approved WBS and estimate both include authorized training work.
  2. Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist.
  3. Milestone status changes only on the documented event rather than elapsed working time.
  4. Responsibility mapping matches decisions to role authority and expertise.

Explanation

Correct Answer

B:

Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist. This validates the selected response: Distinguish product direction from the project's execution, control and delivery baselines. The relevant management principle is: Product plans describe evolving product direction while project plans govern a specific undertaking.

Incorrect Answers

A:

The approved WBS and estimate both include authorized training work. This is evidence for ANOTHER case: A team has a strong cost estimate but has not included training work in the planned scope. The specific corrective response here is: Distinguish product direction from the project's execution, control and delivery baselines.

C:

Milestone status changes only on the documented event rather than elapsed working time. This is evidence for ANOTHER case: A planning analyst records milestones as hours worked and reports inaccurate schedule progress. The specific corrective response here is: Distinguish product direction from the project's execution, control and delivery baselines.

D:

Responsibility mapping matches decisions to role authority and expertise. This is evidence for ANOTHER case: A specialist developer is responsible for test code but is treated as the person who approves project strategy. The specific corrective response here is: Distinguish product direction from the project's execution, control and delivery baselines.

Question 83

For a manufacturing equipment project, the documented failure was: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. Which explanation is most accurate?

  1. Coordinated plans prevent downstream dependencies from being overlooked.
  2. Integrated planning requires traceable governance artifacts and configuration control.
  3. Product plans describe evolving product direction while project plans govern a specific undertaking.
  4. Related project coordination is central to program management.

Explanation

Correct Answer

C:

Product plans describe evolving product direction while project plans govern a specific undertaking. This explains the case: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The targeted action is: Distinguish product direction from the project's execution, control and delivery baselines.

Incorrect Answers

A:

Coordinated plans prevent downstream dependencies from being overlooked. This rationale better explains a DIFFERENT problem: A project changes its customer-facing release date but does not inform warehouse training and support teams. The key mechanism for the current situation is: Product plans describe evolving product direction while project plans govern a specific undertaking.

B:

Integrated planning requires traceable governance artifacts and configuration control. This rationale better explains a DIFFERENT problem: A public-sector project tracks decisions only in hallway conversations and cannot locate baseline approvals. The key mechanism for the current situation is: Product plans describe evolving product direction while project plans govern a specific undertaking.

D:

Related project coordination is central to program management. This rationale better explains a DIFFERENT problem: A construction firm refuses to recognize program dependencies between design, permitting and equipment procurement projects. The key mechanism for the current situation is: Product plans describe evolving product direction while project plans govern a specific undertaking.

Question 84

Which recurring governance check best addresses the risk of repeating: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan.

  1. Audit milestone activities for unintended effort assignment.
  2. Reject nonmeasurable quality definitions at planning review.
  3. Set regular stakeholder feedback and decision checkpoints.
  4. Compare product and project artifacts in kickoff reviews.

Explanation

Correct Answer

D:

Compare product and project artifacts in kickoff reviews. This helps prevent recurrence of: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The required evidence of effective control is: Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist.

Incorrect Answers

A:

Audit milestone activities for unintended effort assignment. That is a useful control for ANOTHER case: A sponsor treats a zero-duration regulatory approval milestone as five days of actual installation effort. The current situation is better prevented by: Compare product and project artifacts in kickoff reviews.

B:

Reject nonmeasurable quality definitions at planning review. That is a useful control for ANOTHER case: A quality plan specifies that software must be excellent but has no measurable tests. The current situation is better prevented by: Compare product and project artifacts in kickoff reviews.

C:

Set regular stakeholder feedback and decision checkpoints. That is a useful control for ANOTHER case: A market-testing initiative keeps an immutable specification after customer interviews reveal the solution solves the wrong need. The current situation is better prevented by: Compare product and project artifacts in kickoff reviews.

Question 85

During a project review, stakeholders report: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager. What should the team do first?

  1. Assign technical delivery accountability to the team and strategy authorization to governance roles.
  2. Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority.
  3. Facilitate a two-way discussion and obtain confirmation of shared meaning.
  4. Track known delays as issues with recovery actions while separately updating future supply risks.

Explanation

Correct Answer

B:

Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority. This addresses the fictional case: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager. The project-management rationale is: Day-to-day coordination differs from sponsor-level authorization and support. Verify by: Team issues are resolved in the correct governance forum without excessive escalations.

Incorrect Answers

A:

Assign technical delivery accountability to the team and strategy authorization to governance roles. This would address a DIFFERENT fictional project situation: A specialist developer is responsible for test code but is treated as the person who approves project strategy. It is less directly applicable to: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

C:

Facilitate a two-way discussion and obtain confirmation of shared meaning. This would address a DIFFERENT fictional project situation: A remote team cannot resolve a misunderstanding because instructions are sent only as one-way technical memos. It is less directly applicable to: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

D:

Track known delays as issues with recovery actions while separately updating future supply risks. This would address a DIFFERENT fictional project situation: A team logs each known supplier delay only as a high probability risk and leaves the issue owner blank. It is less directly applicable to: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

Question 86

Following the proposed correction, what observation confirms success: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

  1. The revised responsibility map includes the required approvals and consultations.
  2. Retrospective feedback shows manageable commitments and improved participation.
  3. Team issues are resolved in the correct governance forum without excessive escalations.
  4. Resolution evidence and closure owner are recorded for the reported complaint.

Explanation

Correct Answer

C:

Team issues are resolved in the correct governance forum without excessive escalations. This validates the selected response: Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority. The relevant management principle is: Day-to-day coordination differs from sponsor-level authorization and support.

Incorrect Answers

A:

The revised responsibility map includes the required approvals and consultations. This is evidence for ANOTHER case: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. The specific corrective response here is: Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority.

B:

Retrospective feedback shows manageable commitments and improved participation. This is evidence for ANOTHER case: A manager spends all team meetings examining metrics but never addresses demotivation following repeated weekend work. The specific corrective response here is: Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority.

D:

Resolution evidence and closure owner are recorded for the reported complaint. This is evidence for ANOTHER case: A software team calls an unresolved customer complaint a constraint despite no policy limiting how it may be resolved. The specific corrective response here is: Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority.

Question 87

Which underlying planning or business-analysis mechanism explains: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

  1. Professional leadership combines accountability with transparent communication.
  2. Team members produce work; governance roles approve strategic direction.
  3. Risk strategies become useful through trigger-driven execution.
  4. Day-to-day coordination differs from sponsor-level authorization and support.

Explanation

Correct Answer

D:

Day-to-day coordination differs from sponsor-level authorization and support. This explains the case: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager. The targeted action is: Let the project manager facilitate routine collaboration and escalate only decisions requiring sponsor authority.

Incorrect Answers

A:

Professional leadership combines accountability with transparent communication. This rationale better explains a DIFFERENT problem: A junior PM withholds forecast problems because they believe leadership means never admitting uncertainty. The key mechanism for the current situation is: Day-to-day coordination differs from sponsor-level authorization and support.

B:

Team members produce work; governance roles approve strategic direction. This rationale better explains a DIFFERENT problem: A specialist developer is responsible for test code but is treated as the person who approves project strategy. The key mechanism for the current situation is: Day-to-day coordination differs from sponsor-level authorization and support.

C:

Risk strategies become useful through trigger-driven execution. This rationale better explains a DIFFERENT problem: A project team identifies a high-probability supplier delay but ignores its approved backup-source risk response. The key mechanism for the current situation is: Day-to-day coordination differs from sponsor-level authorization and support.

Question 88

For the previous project issue, select the best preventive control: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager.

  1. Set escalation thresholds for decisions by role.
  2. Publish approval limits in governance documents.
  3. Validate authority boundaries in RACI matrices.
  4. Trace material response plans to the budget baseline.

Explanation

Correct Answer

A:

Set escalation thresholds for decisions by role. This helps prevent recurrence of: A team expects its sponsor to mediate every daily technical disagreement while refusing to engage the project manager. The required evidence of effective control is: Team issues are resolved in the correct governance forum without excessive escalations.

Incorrect Answers

B:

Publish approval limits in governance documents. That is a useful control for ANOTHER case: A contractor asks the project manager for funding beyond the charter's authority and receives an informal approval. The current situation is better prevented by: Set escalation thresholds for decisions by role.

C:

Validate authority boundaries in RACI matrices. That is a useful control for ANOTHER case: A specialist developer is responsible for test code but is treated as the person who approves project strategy. The current situation is better prevented by: Set escalation thresholds for decisions by role.

D:

Trace material response plans to the budget baseline. That is a useful control for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The current situation is better prevented by: Set escalation thresholds for decisions by role.

Question 89

For a small product delivery team, a delivery problem is reported: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. Which action fits the situation?

  1. Assign benefit ownership and tie prioritized scope to approved value measures.
  2. Run benefit validation using the approved service-time metric and real users.
  3. Follow the agreed communication and escalation plan with verified variance evidence.
  4. Obtain the required intellectual-property authorization before adding the design to deliverables.

Explanation

Correct Answer

C:

Follow the agreed communication and escalation plan with verified variance evidence. This addresses the fictional case: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. The project-management rationale is: Communication strategies define who needs which information and when. Verify by: The sponsor receives timely, accurate escalation and options.

Incorrect Answers

A:

Assign benefit ownership and tie prioritized scope to approved value measures. This would address a DIFFERENT fictional project situation: A sponsor approved a high-level benefit target, but the project team starts building unrelated features because no value owner is identified. It is less directly applicable to: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient.

B:

Run benefit validation using the approved service-time metric and real users. This would address a DIFFERENT fictional project situation: A product experiment delivers a feature but does not measure whether customer service time actually improved. It is less directly applicable to: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient.

D:

Obtain the required intellectual-property authorization before adding the design to deliverables. This would address a DIFFERENT fictional project situation: Two internal departments dispute a licensed design and one party proposes using the material without consent. It is less directly applicable to: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient.

Question 90

How should the project team verify a successful response to: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient.

  1. The benefit report compares before-and-after time with the agreed target.
  2. The mitigation has an assigned owner and funded schedule activities.
  3. Independent evaluation records document a fair, reviewable procurement decision.
  4. The sponsor receives timely, accurate escalation and options.

Explanation

Correct Answer

D:

The sponsor receives timely, accurate escalation and options. This validates the selected response: Follow the agreed communication and escalation plan with verified variance evidence. The relevant management principle is: Communication strategies define who needs which information and when.

Incorrect Answers

A:

The benefit report compares before-and-after time with the agreed target. This is evidence for ANOTHER case: A product experiment delivers a feature but does not measure whether customer service time actually improved. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.

B:

The mitigation has an assigned owner and funded schedule activities. This is evidence for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.

C:

Independent evaluation records document a fair, reviewable procurement decision. This is evidence for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The specific corrective response here is: Follow the agreed communication and escalation plan with verified variance evidence.