Question 20
Atlas Scientific is delivering an IT initiative involving lab collaboration and cloud-hosted research subject to a limited implementation budget. The team observes: A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The approved plan contains controlled phase outputs and formal reviews before dependent work begins. This is the relevant acceptance evidence because it tests whether the corrective action (Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.) fixed the original concern (A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations.) at Atlas Scientific, rather than relying only on a task marked complete. The affected work concerns lab collaboration and cloud-hosted research.
Incorrect Answers
A sprint review delivers working increments and changes future backlog priority without uncontrolled baseline edits. This evidence would be useful for another condition (A product team receives user feedback every week and the required functionality changes frequently but all details are frozen a year ahead.) and its different action (Use an iterative Agile approach with prioritized increments and frequent stakeholder feedback.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved plan contains controlled phase outputs and formal reviews before dependent work begins.
A working increment reaches reviewers early and defects are captured before a large final release. This evidence would be useful for another condition (A software team is asked to develop a very small change through a long batch release despite a requirement for short feedback and continuous improvement.) and its different action (Apply a suitable incremental development practice with test feedback and frequent manageable delivery.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved plan contains controlled phase outputs and formal reviews before dependent work begins.
The board reveals blocked work and a controlled WIP limit reduces multitasking overload. This evidence would be useful for another condition (A project manager tracks software improvements in one large list but cannot see work in progress or overloaded stages.) and its different action (Use a Kanban workflow with explicit states and work-in-progress limits.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved plan contains controlled phase outputs and formal reviews before dependent work begins.