Question 10
Maple Creek Agriculture is delivering an IT initiative involving farm operations and logistics analytics under controlled release and records requirements. The team observes: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
A program-level dependency review coordinates outcomes without erasing each project's authorization. This is the relevant acceptance evidence because it tests whether the corrective action (Manage the independent projects in a coordinated program when their shared benefits require alignment.) fixed the original concern (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) at Maple Creek Agriculture, rather than relying only on a task marked complete. The affected work concerns farm operations and logistics analytics.
Incorrect Answers
The portfolio list separates perpetual support work from the finite payroll migration initiative. This evidence would be useful for another condition (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) and its different action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.
The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.
Sprint selection follows product value and reviewable capacity rather than arbitrary developer preference. This evidence would be useful for another condition (A Scrum group treats a two-week sprint as permission to ignore the product owner's ordered business priorities.) and its different action (Have the product owner manage the backlog priority while the team plans a realistic sprint goal.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.