McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 1

Question 1

Pinecrest Research is delivering an IT initiative involving research data and distributed collaboration subject to a limited implementation budget. The team observes: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. Which project management action BEST addresses the particular issue?

  1. Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.
  2. Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.
  3. Manage the independent projects in a coordinated program when their shared benefits require alignment.
  4. Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.

Explanation

Correct Answer

B:

Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome. This directly addresses the reported management gap: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. For Pinecrest Research and its research data and distributed collaboration, a useful verification outcome is: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Incorrect Answers

A:

Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates. This choice addresses another specific project condition: A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations. The actual issue at Pinecrest Research is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

C:

Manage the independent projects in a coordinated program when their shared benefits require alignment. This choice addresses another specific project condition: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The actual issue at Pinecrest Research is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

D:

Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives. This choice addresses another specific project condition: Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff. The actual issue at Pinecrest Research is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 2

Pinecrest Research is delivering an IT initiative involving research data and distributed collaboration subject to a limited implementation budget. The team observes: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A program-level dependency review coordinates outcomes without erasing each project's authorization.
  2. The portfolio list separates perpetual support work from the finite payroll migration initiative.
  3. The investment review selects and sequences projects without inventing a shared deliverable or deadline.
  4. The approved plan contains controlled phase outputs and formal reviews before dependent work begins.

Explanation

Correct Answer

B:

The portfolio list separates perpetual support work from the finite payroll migration initiative. This is the relevant acceptance evidence because it tests whether the corrective action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.) fixed the original concern (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) at Pinecrest Research, rather than relying only on a task marked complete. The affected work concerns research data and distributed collaboration.

Incorrect Answers

A:

A program-level dependency review coordinates outcomes without erasing each project's authorization. This evidence would be useful for another condition (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) and its different action (Manage the independent projects in a coordinated program when their shared benefits require alignment.). At Pinecrest Research, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

C:

The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Pinecrest Research, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

D:

The approved plan contains controlled phase outputs and formal reviews before dependent work begins. This evidence would be useful for another condition (A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations.) and its different action (Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.). At Pinecrest Research, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 3

For Willowbrook Education, the business analyst reports the following delivery problem: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. Which project management action BEST addresses the particular issue?

  1. Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.
  2. Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.
  3. Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.
  4. Manage the independent projects in a coordinated program when their shared benefits require alignment.

Explanation

Correct Answer

C:

Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome. This directly addresses the reported management gap: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. For Willowbrook Education and its student registration and teacher collaboration, a useful verification outcome is: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Incorrect Answers

A:

Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives. This choice addresses another specific project condition: Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff. The actual issue at Willowbrook Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

B:

Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates. This choice addresses another specific project condition: A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations. The actual issue at Willowbrook Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

D:

Manage the independent projects in a coordinated program when their shared benefits require alignment. This choice addresses another specific project condition: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The actual issue at Willowbrook Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 4

For Willowbrook Education, the business analyst reports the following delivery problem: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The approved plan contains controlled phase outputs and formal reviews before dependent work begins.
  2. The portfolio list separates perpetual support work from the finite payroll migration initiative.
  3. A program-level dependency review coordinates outcomes without erasing each project's authorization.
  4. The investment review selects and sequences projects without inventing a shared deliverable or deadline.

Explanation

Correct Answer

B:

The portfolio list separates perpetual support work from the finite payroll migration initiative. This is the relevant acceptance evidence because it tests whether the corrective action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.) fixed the original concern (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) at Willowbrook Education, rather than relying only on a task marked complete. The affected work concerns student registration and teacher collaboration.

Incorrect Answers

A:

The approved plan contains controlled phase outputs and formal reviews before dependent work begins. This evidence would be useful for another condition (A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations.) and its different action (Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.). At Willowbrook Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

C:

A program-level dependency review coordinates outcomes without erasing each project's authorization. This evidence would be useful for another condition (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) and its different action (Manage the independent projects in a coordinated program when their shared benefits require alignment.). At Willowbrook Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

D:

The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Willowbrook Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 5

At Crescent Education, the delivery assessment finds: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. Which project management action BEST addresses the particular issue?

  1. Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.
  2. Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.
  3. Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.
  4. Manage the independent projects in a coordinated program when their shared benefits require alignment.

Explanation

Correct Answer

A:

Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome. This directly addresses the reported management gap: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. For Crescent Education and its learning platforms and staff accounts, a useful verification outcome is: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Incorrect Answers

B:

Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives. This choice addresses another specific project condition: Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff. The actual issue at Crescent Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

C:

Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates. This choice addresses another specific project condition: A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations. The actual issue at Crescent Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

D:

Manage the independent projects in a coordinated program when their shared benefits require alignment. This choice addresses another specific project condition: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The actual issue at Crescent Education is: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. That other intervention does not itself establish the required result: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 6

At Crescent Education, the delivery assessment finds: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A program-level dependency review coordinates outcomes without erasing each project's authorization.
  2. The investment review selects and sequences projects without inventing a shared deliverable or deadline.
  3. The approved plan contains controlled phase outputs and formal reviews before dependent work begins.
  4. The portfolio list separates perpetual support work from the finite payroll migration initiative.

Explanation

Correct Answer

D:

The portfolio list separates perpetual support work from the finite payroll migration initiative. This is the relevant acceptance evidence because it tests whether the corrective action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.) fixed the original concern (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) at Crescent Education, rather than relying only on a task marked complete. The affected work concerns learning platforms and staff accounts.

Incorrect Answers

A:

A program-level dependency review coordinates outcomes without erasing each project's authorization. This evidence would be useful for another condition (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) and its different action (Manage the independent projects in a coordinated program when their shared benefits require alignment.). At Crescent Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

B:

The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Crescent Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

C:

The approved plan contains controlled phase outputs and formal reviews before dependent work begins. This evidence would be useful for another condition (A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations.) and its different action (Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.). At Crescent Education, it does not demonstrate the required project outcome: The portfolio list separates perpetual support work from the finite payroll migration initiative.

Question 7

At Cedar City Utilities, the delivery assessment finds: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. Which project management action BEST addresses the particular issue?

  1. Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.
  2. Manage the independent projects in a coordinated program when their shared benefits require alignment.
  3. Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.
  4. Have the product owner manage the backlog priority while the team plans a realistic sprint goal.

Explanation

Correct Answer

B:

Manage the independent projects in a coordinated program when their shared benefits require alignment. This directly addresses the reported management gap: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. For Cedar City Utilities and its metering systems and billing applications, a useful verification outcome is: A program-level dependency review coordinates outcomes without erasing each project's authorization.

Incorrect Answers

A:

Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives. This choice addresses another specific project condition: Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff. The actual issue at Cedar City Utilities is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

C:

Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome. This choice addresses another specific project condition: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. The actual issue at Cedar City Utilities is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

D:

Have the product owner manage the backlog priority while the team plans a realistic sprint goal. This choice addresses another specific project condition: A Scrum group treats a two-week sprint as permission to ignore the product owner's ordered business priorities. The actual issue at Cedar City Utilities is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

Question 8

At Cedar City Utilities, the delivery assessment finds: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The investment review selects and sequences projects without inventing a shared deliverable or deadline.
  2. The portfolio list separates perpetual support work from the finite payroll migration initiative.
  3. A program-level dependency review coordinates outcomes without erasing each project's authorization.
  4. Sprint selection follows product value and reviewable capacity rather than arbitrary developer preference.

Explanation

Correct Answer

C:

A program-level dependency review coordinates outcomes without erasing each project's authorization. This is the relevant acceptance evidence because it tests whether the corrective action (Manage the independent projects in a coordinated program when their shared benefits require alignment.) fixed the original concern (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) at Cedar City Utilities, rather than relying only on a task marked complete. The affected work concerns metering systems and billing applications.

Incorrect Answers

A:

The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Cedar City Utilities, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.

B:

The portfolio list separates perpetual support work from the finite payroll migration initiative. This evidence would be useful for another condition (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) and its different action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.). At Cedar City Utilities, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.

D:

Sprint selection follows product value and reviewable capacity rather than arbitrary developer preference. This evidence would be useful for another condition (A Scrum group treats a two-week sprint as permission to ignore the product owner's ordered business priorities.) and its different action (Have the product owner manage the backlog priority while the team plans a realistic sprint goal.). At Cedar City Utilities, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.

Question 9

Maple Creek Agriculture is delivering an IT initiative involving farm operations and logistics analytics under controlled release and records requirements. The team observes: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. Which project management action BEST addresses the particular issue?

  1. Manage the independent projects in a coordinated program when their shared benefits require alignment.
  2. Have the product owner manage the backlog priority while the team plans a realistic sprint goal.
  3. Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.
  4. Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.

Explanation

Correct Answer

A:

Manage the independent projects in a coordinated program when their shared benefits require alignment. This directly addresses the reported management gap: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. For Maple Creek Agriculture and its farm operations and logistics analytics, a useful verification outcome is: A program-level dependency review coordinates outcomes without erasing each project's authorization.

Incorrect Answers

B:

Have the product owner manage the backlog priority while the team plans a realistic sprint goal. This choice addresses another specific project condition: A Scrum group treats a two-week sprint as permission to ignore the product owner's ordered business priorities. The actual issue at Maple Creek Agriculture is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

C:

Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome. This choice addresses another specific project condition: A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end. The actual issue at Maple Creek Agriculture is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

D:

Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives. This choice addresses another specific project condition: Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff. The actual issue at Maple Creek Agriculture is: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. That other intervention does not itself establish the required result: A program-level dependency review coordinates outcomes without erasing each project's authorization.

Question 10

Maple Creek Agriculture is delivering an IT initiative involving farm operations and logistics analytics under controlled release and records requirements. The team observes: Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The portfolio list separates perpetual support work from the finite payroll migration initiative.
  2. The investment review selects and sequences projects without inventing a shared deliverable or deadline.
  3. Sprint selection follows product value and reviewable capacity rather than arbitrary developer preference.
  4. A program-level dependency review coordinates outcomes without erasing each project's authorization.

Explanation

Correct Answer

D:

A program-level dependency review coordinates outcomes without erasing each project's authorization. This is the relevant acceptance evidence because it tests whether the corrective action (Manage the independent projects in a coordinated program when their shared benefits require alignment.) fixed the original concern (Three unrelated technology upgrades are treated as one project even though each has a separate charter and sponsor.) at Maple Creek Agriculture, rather than relying only on a task marked complete. The affected work concerns farm operations and logistics analytics.

Incorrect Answers

A:

The portfolio list separates perpetual support work from the finite payroll migration initiative. This evidence would be useful for another condition (A PM describes the ongoing payroll help-desk operation as a project although it has no unique deliverable or planned end.) and its different action (Classify the recurring support work as operations and reserve a project designation for a temporary unique outcome.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.

B:

The investment review selects and sequences projects without inventing a shared deliverable or deadline. This evidence would be useful for another condition (Leadership combines a customer portal launch and an unrelated server replacement into one delivery schedule merely because both use IT staff.) and its different action (Use portfolio governance to prioritize the separate initiatives against investment and strategic objectives.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.

C:

Sprint selection follows product value and reviewable capacity rather than arbitrary developer preference. This evidence would be useful for another condition (A Scrum group treats a two-week sprint as permission to ignore the product owner's ordered business priorities.) and its different action (Have the product owner manage the backlog priority while the team plans a realistic sprint goal.). At Maple Creek Agriculture, it does not demonstrate the required project outcome: A program-level dependency review coordinates outcomes without erasing each project's authorization.