Question 40
For Ridgeview Finance, the implementation team reports the following delivery problem: A project manager tracks software improvements in one large list but cannot see work in progress or overloaded stages. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The board reveals blocked work and a controlled WIP limit reduces multitasking overload. This is the relevant acceptance evidence because it tests whether the corrective action (Use a Kanban workflow with explicit states and work-in-progress limits.) fixed the original concern (A project manager tracks software improvements in one large list but cannot see work in progress or overloaded stages.) at Ridgeview Finance, rather than relying only on a task marked complete. The affected work concerns financial reporting and customer portals.
Incorrect Answers
The approved plan contains controlled phase outputs and formal reviews before dependent work begins. This evidence would be useful for another condition (A new software project has a fixed mandated sequence of approved requirements and milestone signoffs but the manager starts unstructured iterations.) and its different action (Select a predictive waterfall approach appropriate to fixed requirements and sequential approval gates.). At Ridgeview Finance, it does not demonstrate the required project outcome: The board reveals blocked work and a controlled WIP limit reduces multitasking overload.
The release evidence shows automated security checks and owner-reviewed exceptions before deployment. This evidence would be useful for another condition (A regulated release needs audit evidence of security checks but the pipeline only automates code compilation and ignores security tasks.) and its different action (Integrate appropriate security validation into the DevSecOps development and deployment workflow.). At Ridgeview Finance, it does not demonstrate the required project outcome: The board reveals blocked work and a controlled WIP limit reduces multitasking overload.
A working increment reaches reviewers early and defects are captured before a large final release. This evidence would be useful for another condition (A software team is asked to develop a very small change through a long batch release despite a requirement for short feedback and continuous improvement.) and its different action (Apply a suitable incremental development practice with test feedback and frequent manageable delivery.). At Ridgeview Finance, it does not demonstrate the required project outcome: The board reveals blocked work and a controlled WIP limit reduces multitasking overload.