Question 420
An administrator needs to move a member from ElasticXL Site 1 into Site 2. It already appears as a managed member of Site 1, so it is not pending for enrollment in the second site. A proposed change would be to connect Sync ports through dedicated Layer 2 switching or VLAN, which addresses the different requirement to provide the transport for cluster member synchronization. Which action instead addresses the observed incident?
Explanation
Correct Answer
The documented workflow removes and re-adds a node to the chosen site. This directly addresses the documented incident evidence.
Incorrect Answers
A new site is used to establish High Availability sites; this does not resolve the observed condition.
Adding to the existing site enables supported load sharing, yet that applies to increase capacity inside an existing ElasticXL Site rather than the observed issue.