Question 180
The central operations team wants to schedule supported software maintenance for a cluster through SmartConsole and track it in Tasks. A new Access Control policy is not the deliverable. Which managed deployment interface should the operator use?
Explanation
Correct Answer
Use the Gateways & Servers deployment Actions for the selected gateway or full cluster target.
Incorrect Answers
Installing an arbitrary hotfix is premature until the maintenance action and package are selected.
CDT execution may be available but is not the GUI workflow specified for this change.
Version Upgrade is only one possible action and should not be selected without a version change.