Question 520
While planning a VCF platform for subscriber provisioning at a telecommunications operator, stakeholders discover: The project proposes migrating application VMs without checking the supported VM hardware and platform versions. Which decision is most defensible?
Explanation
Correct Answer
The most direct design decision is to validate compatibility and supported migration paths before wave planning. For subscriber provisioning at a telecommunications operator, the stated problem is: The project proposes migrating application VMs without checking the supported VM hardware and platform versions. That approach addresses the documented architecture objective rather than an unrelated implementation detail. It should be accepted when the migration plan names verified supported source and target combinations. The design choice remains subject to the real environment's compatibility and constraints.
Incorrect Answers
Choose a supported network transition or application remediation strategy addresses the separate architecture topic of network address continuity, where the underlying concern is: An application uses hard-coded IP dependencies and the destination design changes addressing without a plan. It does not most directly resolve the present issue for subscriber provisioning at a telecommunications operator: The project proposes migrating application VMs without checking the supported VM hardware and platform versions. The targeted decision is instead to validate compatibility and supported migration paths before wave planning.
Create and verify the required recovery point before executing the migration addresses the separate architecture topic of data protection before cutover, where the underlying concern is: A database cutover begins with no validated backup or recovery point for rollback. It does not most directly resolve the present issue for subscriber provisioning at a telecommunications operator: The project proposes migrating application VMs without checking the supported VM hardware and platform versions. The targeted decision is instead to validate compatibility and supported migration paths before wave planning.
Group migration waves by application dependencies and required sequencing addresses the separate architecture topic of migration dependency waves, where the underlying concern is: The team migrates web servers independently of database and identity dependencies without assessing cutover risk. It does not most directly resolve the present issue for subscriber provisioning at a telecommunications operator: The project proposes migrating application VMs without checking the supported VM hardware and platform versions. The targeted decision is instead to validate compatibility and supported migration paths before wave planning.