Question 320
At fictional Hawthorne Credit Union, the SPM implementation team is supporting a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: Imported project tasks have predecessor IDs mapped as free text rather than task relationships, breaking the schedule network. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Regression-test imported projects with dependencies and milestones. The check is important because a spreadsheet's textual IDs are not automatically equivalent to native relationship records.
Incorrect Answers
Audit roll-up calculations when project structures change. This is a separate preventive check. Project hierarchy aggregation must not add the same underlying expenditure at parent and child levels. To address recurrence here, regression-test imported projects with dependencies and milestones.
Reconcile planned-versus-actual effort at project review. This is a separate preventive check. Planned commitments do not prove executed labor, and their metrics answer different questions. To address recurrence here, regression-test imported projects with dependencies and milestones.
Require diagnostics and evidence on recurring schedule exceptions. This is a separate preventive check. Focused schedule diagnostics isolate structural faults better than speculative date adjustments. To address recurrence here, regression-test imported projects with dependencies and milestones.