Question 340
In an authorized test at fictional Silverbrook Insurance, the project team is assessing a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: A project moves to closed state with open vendor actions and untransferred support ownership. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Review closure exception patterns with the PMO. This prevents the same failure mode, in which project administrative closure should follow delivery acceptance and operational transition.
Incorrect Answers
Reconcile approved demand start dates against capacity plans regularly. Planning intent is not equivalent to a staffed and funded execution commitment. It would not maintain the control needed here: review closure exception patterns with the PMO.
Define return-for-revision transitions and retention rules. Governed lifecycle reversals should preserve historical decisions rather than erase evidence. It would not maintain the control needed here: review closure exception patterns with the PMO.
Audit roll-up calculations when project structures change. Project hierarchy aggregation must not add the same underlying expenditure at parent and child levels. It would not maintain the control needed here: review closure exception patterns with the PMO.