Question 310
In an authorized test at fictional Larkspur Water Authority, the project team is assessing a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: A task has a fixed finish constraint earlier than its predecessor's actual completion, leaving impossible planned dates. The reviewers must preserve traceability and test the selected response before accepting it. What review practice best reduces the recurrence risk?
Explanation
Correct Answer
Review hard-date constraints during schedule changes. This prevents the same failure mode, in which constraints cannot override the physical sequence of dependent work without changing the work plan.
Incorrect Answers
Review dependency ordering during critical-path analysis. Dependency direction determines which activity must happen before another. It would not maintain the control needed here: review hard-date constraints during schedule changes.
Trigger resource impact review for major date or scope changes. Compressing a work window changes required concurrent capacity even when total effort stays constant. It would not maintain the control needed here: review hard-date constraints during schedule changes.
Review phase/resource alignment whenever task dates move. Resource demand must be connected to when specific project work occurs. It would not maintain the control needed here: review hard-date constraints during schedule changes.