Question 290
At fictional Calder Health Network, the SPM implementation team is supporting a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: A deployment project plans go-live before a shared platform upgrade that another project must complete first. The reviewers must preserve traceability and test the selected response before accepting it. What review practice best reduces the recurrence risk?
Explanation
Correct Answer
Reconcile interproject milestones in program governance. The check is important because cross-project dependencies transmit schedule constraints beyond a single project's task list.
Incorrect Answers
Require diagnostics and evidence on recurring schedule exceptions. This is a separate preventive check. Focused schedule diagnostics isolate structural faults better than speculative date adjustments. To address recurrence here, reconcile interproject milestones in program governance.
Reconcile dashboard date sources after workspace configuration changes. This is a separate preventive check. A report must distinguish authorized commitments from working forecast revisions. To address recurrence here, reconcile interproject milestones in program governance.
Reassess dependency and capacity assumptions for any baseline rollback. This is a separate preventive check. A historic baseline is a comparison artifact, not proof that conditions still allow its original dates. To address recurrence here, reconcile interproject milestones in program governance.