Question 280
In an authorized test at fictional Clearhaven Retail, the project team is assessing a multi-region program rollout. During a quarterly audit checkpoint, they find this specific issue: A project manager sets a release gate as a ten-day work task even though it represents a point-in-time acceptance event. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Check milestone logic when editing project schedules. This prevents the same failure mode, in which milestones mark significant events, while effort-bearing tasks represent actual work over time.
Incorrect Answers
Review phase/resource alignment whenever task dates move. Resource demand must be connected to when specific project work occurs. It would not maintain the control needed here: check milestone logic when editing project schedules.
Review stagnant high-percentage tasks for hidden blockers. Progress percentage requires observable delivery evidence to support realistic forecasts. It would not maintain the control needed here: check milestone logic when editing project schedules.
Review abandoned ideas and intake aging with designated owners. Idea intake collects potential investments before they become evaluated and committed demand. It would not maintain the control needed here: check milestone logic when editing project schedules.