Question 730
The project team reports that it resolved the following issue: A community irrigation project has one manager acting as both project manager and team manager, and no written distinction between acceptance and stage reporting. Which observed result is the best acceptance evidence?
Explanation
Correct Answer
The strongest confirmation is: Product delivery and project stage records separately show what was authorized and what was accepted. It is evidence for the specific corrective step—Tailor the work package and reporting arrangements while retaining explicit acceptance criteria and product verification.—rather than a generic system-health signal.
Incorrect Answers
That outcome could matter in a case where specialist delivery has omitted a required part of the accepted product definition, but the present check needs to show that product delivery and project stage records separately show what was authorized and what was accepted.
That outcome could matter in a case where the formal handover of completed specialist work is disconnected from stage progress control, but the present check needs to show that product delivery and project stage records separately show what was authorized and what was accepted.
It would be evidence for a problem in which the team manager is not providing agreed specialist delivery control information to the project manager. It does not verify that product delivery and project stage records separately show what was authorized and what was accepted.