Question 710
A PRINCE2 practitioner has implemented a correction to this situation: A cloud integration supplier discovers its assigned interface will require additional product scope and unilaterally changes the design. Which outcome demonstrates that the correction worked?
Explanation
Correct Answer
This finding directly demonstrates the intended result: The additional interface is built only after an authorized decision and updated package description. It tests whether the chosen remediation—Raise the change through the project manager and follow the agreed issue and work package control.—has addressed the cause: The team manager has exceeded work package scope without seeking issue assessment or authorization.
Incorrect Answers
This result could confirm a fix when agile team routines have not been connected to PRINCE2 work package reporting and control. It would not demonstrate that the additional interface is built only after an authorized decision and updated package description.
It would be evidence for a problem in which the team manager is failing to escalate an urgent threat to safe product delivery. It does not verify that the additional interface is built only after an authorized decision and updated package description.
This result could confirm a fix when the team manager has started specialist delivery without agreeing the work package's products, criteria or limits. It would not demonstrate that the additional interface is built only after an authorized decision and updated package description.