Question 700
What recurring PRINCE2 control would best prevent this situation from happening again? A solar farm supplier begins work on an inverter configuration before accepting the project manager's work package requirements.
Explanation
Correct Answer
The lasting control is: Require explicit work package acceptance before scheduling specialist delivery. It addresses recurrence of this mechanism: The team manager has started specialist delivery without agreeing the work package's products, criteria or limits. A successful system should still demonstrate: Both parties retain an accepted package defining configuration outcomes, quality and checkpoints.
Incorrect Answers
This measure addresses a risk where the formal handover of completed specialist work is disconnected from stage progress control. The recurring failure here arises because the team manager has started specialist delivery without agreeing the work package's products, criteria or limits.
The proposed routine targets situations in which the team manager has exceeded work package scope without seeking issue assessment or authorization. To prevent the reported problem, the team must address the fact that the team manager has started specialist delivery without agreeing the work package's products, criteria or limits.
The option addresses cases in which the team manager is not providing agreed specialist delivery control information to the project manager. In the reported incident, the team manager has started specialist delivery without agreeing the work package's products, criteria or limits instead.