Question 680
Choose the most relevant preventive check for this PRINCE2 project situation: A city hospital refurbishment forecasts a cost overrun greater than the delegated stage tolerance, but the project manager approves the extra spend.
Explanation
Correct Answer
To prevent the same issue, apply this check: Make stage tolerance forecast checks a gate for spending commitments. The risk to contain is: The project manager is exceeding management by exception authority for the current stage. Verify control effectiveness using: The board considers the forecast breach and authorizes any replacement plan within its authority.
Incorrect Answers
This measure addresses a risk where incomplete work has been concealed in an informal plan shift rather than controlled at the stage boundary. The recurring failure here arises because the project manager is exceeding management by exception authority for the current stage.
The control would be appropriate if the stage control process is not assessing and responding to issues in time; the issue here is that the project manager is exceeding management by exception authority for the current stage.
This measure addresses a risk where stage progress control is focused on historical achievement rather than future tolerance exposure. The recurring failure here arises because the project manager is exceeding management by exception authority for the current stage.