Question 660
The project team has corrected the following defect: A small school website project proposes dozens of management documents copied from a national programme template. Which future assurance check should be added?
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Review document burden and control value during project initiation and at later boundaries. The original root fault was: The initiating process has not tailored controls to project size, risk and team structure. The practical health indicator is: The PID provides sufficient control with a manageable number of maintained artifacts.
Incorrect Answers
This measure addresses a risk where project initiation omitted an explicit approach for managing an agreed performance target. The recurring failure here arises because the initiating process has not tailored controls to project size, risk and team structure.
The control would be appropriate if the change management approach is missing from initiation despite significant people impacts; the issue here is that the initiating process has not tailored controls to project size, risk and team structure.
The control would be appropriate if the PID decision package is missing an updated investment justification; the issue here is that the initiating process has not tailored controls to project size, risk and team structure.