Question 650
The board requests proof that this project fault is controlled: A transport authority designs stage tolerances but the project manager and board disagree on forecast reporting frequency. Which result is most relevant?
Explanation
Correct Answer
This finding directly demonstrates the intended result: Highlight and checkpoint expectations are documented and align with the level of delegated authority. It tests whether the chosen remediation—Set stage controls, tolerances and reporting cadence in the PID with board and team input.—has addressed the cause: Project controls and information needs have not been agreed as part of initiation.
Incorrect Answers
This result could confirm a fix when the initiating process has not established the baseline management controls required for predictable delivery. It would not demonstrate that highlight and checkpoint expectations are documented and align with the level of delegated authority.
That outcome could matter in a case where the digital and data management approach has not been defined for project information reliability, but the present check needs to show that highlight and checkpoint expectations are documented and align with the level of delegated authority.
It would be evidence for a problem in which the change management approach is missing from initiation despite significant people impacts. It does not verify that highlight and checkpoint expectations are documented and align with the level of delegated authority.