Question 500
A Practitioner recommends a permanent improvement after this problem: A coastal resilience project agrees a design change orally during a site visit but the project log records no rationale. Which control is most effective?
Explanation
Correct Answer
To prevent the same issue, apply this check: Prohibit undocumented scope changes and check work against approved baselines. The risk to contain is: A significant change has been made without an auditable issue decision. Verify control effectiveness using: The changed drawing and stage plan carry a traceable recorded issue decision.
Incorrect Answers
This safeguard is useful when a reported concern or suggestion has been assumed to change a baseline before impact assessment. It does not prevent the present fault, where a significant change has been made without an auditable issue decision.
This safeguard is useful when the team is evaluating a change's value without analyzing its full effect on time and compliance. It does not prevent the present fault, where a significant change has been made without an auditable issue decision.
The proposed routine targets situations in which the issue lacks analysis needed for a sound decision. To prevent the reported problem, the team must address the fact that a significant change has been made without an auditable issue decision.