Question 480
Which ongoing review or control is most appropriate for avoiding a repeat of the following project incident? A water-monitoring project asks an informal steering group to authorize a change that exceeds project-level time tolerance.
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Include tolerance and authority checks in every change approval route. The original root fault was: An approval body is being used beyond its formal authority and tolerance delegation. The practical health indicator is: The decision is recorded by the body holding authority over the affected project tolerance.
Incorrect Answers
The proposed routine targets situations in which issue management is being limited to approved changes rather than covering concerns and problems. To prevent the reported problem, the team must address the fact that an approval body is being used beyond its formal authority and tolerance delegation.
The option addresses cases in which the positive option has not been assessed across its potential benefits and stage tolerances. In the reported incident, an approval body is being used beyond its formal authority and tolerance delegation instead.
This safeguard is useful when the issue lacks analysis needed for a sound decision. It does not prevent the present fault, where an approval body is being used beyond its formal authority and tolerance delegation.