Question 520
The project team has corrected the following defect: An application migration project produces a daily task log but lacks any summary of lessons for the next management stage. Which future assurance check should be added?
Explanation
Correct Answer
The lasting control is: Include lessons review in each end stage report and handover decision. It addresses recurrence of this mechanism: The project log is maintained without analyzing useful experience and communicating it at boundaries. A successful system should still demonstrate: The next stage plan demonstrates action on the documented lessons report.
Incorrect Answers
This measure addresses a risk where the exception trigger is based on actual variance rather than the forecast breach of delegated tolerance. The recurring failure here arises because the project log is maintained without analyzing useful experience and communicating it at boundaries.
The control would be appropriate if progress controls omit an agreed project performance target and therefore hide possible tolerance exposure; the issue here is that the project log is maintained without analyzing useful experience and communicating it at boundaries.
The option addresses cases in which the digital and data management approach has not established provenance, access and reliability of management information. In the reported incident, the project log is maintained without analyzing useful experience and communicating it at boundaries instead.