Question 460
A project assurance review examines the cause of this problem: A park-renewal client asks for an extra public walkway after the baseline scope was approved. What preventive action should be introduced?
Explanation
Correct Answer
The lasting control is: Route scope additions through a controlled issue and change workflow. It addresses recurrence of this mechanism: A request for change is being performed without impact assessment or a decision. A successful system should still demonstrate: The implemented change has a signed decision and updated product and plan baselines.
Incorrect Answers
The proposed routine targets situations in which the issue lacks analysis needed for a sound decision. To prevent the reported problem, the team must address the fact that a request for change is being performed without impact assessment or a decision.
The proposed routine targets situations in which the team is evaluating a change's value without analyzing its full effect on time and compliance. To prevent the reported problem, the team must address the fact that a request for change is being performed without impact assessment or a decision.
This safeguard is useful when the off-specification assertion cannot be reconciled with the agreed product baseline. It does not prevent the present fault, where a request for change is being performed without impact assessment or a decision.