Question 440
After dealing with this project failure—A climate adaptation scheme identifies an uncertain cost shock but does not distinguish its effect on project tolerance from its stage tolerance.—which governance safeguard should be retained?
Explanation
Correct Answer
To prevent the same issue, apply this check: Include tolerance exposure in risk impact fields and escalation criteria. The risk to contain is: Risk escalation is not linked to the level at which the exposure could exceed delegated limits. Verify control effectiveness using: The risk response and exception decisions use the appropriate governance thresholds.
Incorrect Answers
This safeguard is useful when the designated risk owner does not have appropriate accountability or decision authority for the response. It does not prevent the present fault, where risk escalation is not linked to the level at which the exposure could exceed delegated limits.
The proposed routine targets situations in which an event that has already occurred is being managed as an uncertain future risk rather than a current issue. To prevent the reported problem, the team must address the fact that risk escalation is not linked to the level at which the exposure could exceed delegated limits.
The control would be appropriate if distinct threats with different causes and controls have been inappropriately merged; the issue here is that risk escalation is not linked to the level at which the exposure could exceed delegated limits.