Question 420
What recurring PRINCE2 control would best prevent this situation from happening again? A rail platform upgrade has a potential weather delay and a separate safety risk, but a single generic risk response covers both.
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Review risks for independent causes before consolidating exposures. The original root fault was: Distinct threats with different causes and controls have been inappropriately merged. The practical health indicator is: Each risk has its own trigger, impact, accountable owner and tested response plan.
Incorrect Answers
The option addresses cases in which risk acceptance has bypassed project risk tolerance and the relevant risk decision authority. In the reported incident, distinct threats with different causes and controls have been inappropriately merged instead.
This measure addresses a risk where the chosen response creates a new threat that has not been evaluated against project objectives. The recurring failure here arises because distinct threats with different causes and controls have been inappropriately merged.
This safeguard is useful when risk management has become a static document instead of an ongoing stage control. It does not prevent the present fault, where distinct threats with different causes and controls have been inappropriately merged.