McAfee-Secured Website

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

100% PRINCE2 PRINCE2 7 Practitioner Guaranteed Success With Testking Training Materials

Get Real PRINCE2 7 Practitioner Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 41

Question 400

Choose the most relevant preventive check for this PRINCE2 project situation: A public records modernization project assigns a major data-loss threat to a supplier with no authority to change internal backup controls.

  1. Apply the same disciplined evaluation to opportunities as to threats.
  2. Review risk status and convert realized threats into issue control promptly.
  3. Make risk review part of routine work package reporting and stage controls.
  4. Review risk ownership and response authority whenever threats cross organizational boundaries.

Explanation

Correct Answer

D:

The lasting control is: Review risk ownership and response authority whenever threats cross organizational boundaries. It addresses recurrence of this mechanism: The designated risk owner does not have appropriate accountability or decision authority for the response. A successful system should still demonstrate: The register identifies accountable oversight and implementable actions with due dates.

Incorrect Answers

A:

The proposed routine targets situations in which the opportunity is recorded as guaranteed rather than assessed for contingent benefits and constraints. To prevent the reported problem, the team must address the fact that the designated risk owner does not have appropriate accountability or decision authority for the response.

B:

The proposed routine targets situations in which an event that has already occurred is being managed as an uncertain future risk rather than a current issue. To prevent the reported problem, the team must address the fact that the designated risk owner does not have appropriate accountability or decision authority for the response.

C:

This measure addresses a risk where risk management has become a static document instead of an ongoing stage control. The recurring failure here arises because the designated risk owner does not have appropriate accountability or decision authority for the response.

Question 401

A practitioner must act on this project issue: A rural broadband project treats the possibility of accelerated access approvals only as an issue to ignore until the approvals arrive. Which intervention most directly addresses the failure?

  1. Develop a feasible fallback supplier or inventory option and assign its trigger and action owner.
  2. Record and assess the opportunity with a proportionate exploitation or enhancement response.
  3. Assess the reuse opportunity's probability, value and licensing dependencies before committing savings.
  4. Use relevant historical data and specialist analysis to inform probability and impact before selecting the response.

Explanation

Correct Answer

B:

The case requires this change: Record and assess the opportunity with a proportionate exploitation or enhancement response. The actual failure mechanism is: A beneficial uncertain event has not been identified and managed as an opportunity. A meaningful acceptance check is: The project has a controlled plan to benefit from early approval without violating authorization limits.

Incorrect Answers

A:

“Develop a feasible fallback supplier or inventory option and assign its trigger and action owner” is useful when a material dependency risk has no planned response despite high stage impact. It does not resolve the current problem, in which a beneficial uncertain event has not been identified and managed as an opportunity.

C:

That action tackles a problem where the opportunity is recorded as guaranteed rather than assessed for contingent benefits and constraints. The reported issue is instead that a beneficial uncertain event has not been identified and managed as an opportunity.

D:

The option would help when risk assessment is insufficiently evidence-based for a material technical exposure, but it would not address a situation where a beneficial uncertain event has not been identified and managed as an opportunity.

Question 402

A PRINCE2 practitioner has implemented a correction to this situation: A rural broadband project treats the possibility of accelerated access approvals only as an issue to ignore until the approvals arrive. Which outcome demonstrates that the correction worked?

  1. Each risk has its own trigger, impact, accountable owner and tested response plan.
  2. The selected mitigation preserves recovery capability and documents its residual risks.
  3. The risk register cites a defensible evidence basis and revised response priorities.
  4. The project has a controlled plan to benefit from early approval without violating authorization limits.

Explanation

Correct Answer

D:

Successful remediation is demonstrated when: The project has a controlled plan to benefit from early approval without violating authorization limits. That result connects to the targeted action: Record and assess the opportunity with a proportionate exploitation or enhancement response. The previously observed defect was: A beneficial uncertain event has not been identified and managed as an opportunity.

Incorrect Answers

A:

It would be evidence for a problem in which distinct threats with different causes and controls have been inappropriately merged. It does not verify that the project has a controlled plan to benefit from early approval without violating authorization limits.

B:

This result could confirm a fix when the chosen response creates a new threat that has not been evaluated against project objectives. It would not demonstrate that the project has a controlled plan to benefit from early approval without violating authorization limits.

C:

The observation relates to a problem where risk assessment is insufficiently evidence-based for a material technical exposure; the required finding here is that the project has a controlled plan to benefit from early approval without violating authorization limits.

Question 403

A project assurance reviewer investigates the following: A rural broadband project treats the possibility of accelerated access approvals only as an issue to ignore until the approvals arrive. What is the root cause?

  1. A beneficial uncertain event has not been identified and managed as an opportunity.
  2. The opportunity is recorded as guaranteed rather than assessed for contingent benefits and constraints.
  3. A material dependency risk has no planned response despite high stage impact.
  4. Risk management has become a static document instead of an ongoing stage control.

Explanation

Correct Answer

A:

This mechanism accounts for the observation: A beneficial uncertain event has not been identified and managed as an opportunity. Address it by implementing: Record and assess the opportunity with a proportionate exploitation or enhancement response. Confirm the fix through: The project has a controlled plan to benefit from early approval without violating authorization limits.

Incorrect Answers

B:

The proposed diagnosis concerns a problem where the opportunity is recorded as guaranteed rather than assessed for contingent benefits and constraints. The facts here indicate that a beneficial uncertain event has not been identified and managed as an opportunity.

C:

This diagnosis fits a situation in which a material dependency risk has no planned response despite high stage impact. Here, a beneficial uncertain event has not been identified and managed as an opportunity.

D:

The cause in this option would matter if risk management has become a static document instead of an ongoing stage control. The reported failure instead arises because a beneficial uncertain event has not been identified and managed as an opportunity.

Question 404

A project assurance review examines the cause of this problem: A rural broadband project treats the possibility of accelerated access approvals only as an issue to ignore until the approvals arrive. What preventive action should be introduced?

  1. Review risk status and convert realized threats into issue control promptly.
  2. Require explicit residual-risk assessment after every response.
  3. Review risk response triggers in operational readiness exercises.
  4. Include opportunities as well as threats in risk identification workshops.

Explanation

Correct Answer

D:

To prevent the same issue, apply this check: Include opportunities as well as threats in risk identification workshops. The risk to contain is: A beneficial uncertain event has not been identified and managed as an opportunity. Verify control effectiveness using: The project has a controlled plan to benefit from early approval without violating authorization limits.

Incorrect Answers

A:

The option addresses cases in which an event that has already occurred is being managed as an uncertain future risk rather than a current issue. In the reported incident, a beneficial uncertain event has not been identified and managed as an opportunity instead.

B:

The proposed routine targets situations in which a mitigation that reduces consequences is being confused with full transfer of responsibility or exposure. To prevent the reported problem, the team must address the fact that a beneficial uncertain event has not been identified and managed as an opportunity.

C:

The control would be appropriate if the risk response lacks an executable activation condition and owner; the issue here is that a beneficial uncertain event has not been identified and managed as an opportunity.

Question 405

Apply PRINCE2 to this project decision: A laboratory refurbishment team reduces the likelihood score of an asbestos discovery risk but makes no actual change to exposure controls. Which response is best supported by the method?

  1. Appoint a risk owner capable of oversight and name an action owner for the specific backup mitigation tasks.
  2. Plan and execute appropriate surveys and containment measures, then reassess residual exposure.
  3. Assess the forecast effect against both stage and project tolerances and route escalation to the correct authority.
  4. Record the actual delay as an issue and assess remaining uncertain consequences as distinct risks.

Explanation

Correct Answer

B:

Choose this fix: Plan and execute appropriate surveys and containment measures, then reassess residual exposure. It repairs the stated issue, where the risk register score has been adjusted without implementing a response or new evidence. The result should be independently established through: Documented surveys and controls support the new risk score and remaining exposure.

Incorrect Answers

A:

“Appoint a risk owner capable of oversight and name an action owner for the specific backup mitigation tasks” is useful when the designated risk owner does not have appropriate accountability or decision authority for the response. It does not resolve the current problem, in which the risk register score has been adjusted without implementing a response or new evidence.

C:

The option would help when risk escalation is not linked to the level at which the exposure could exceed delegated limits, but it would not address a situation where the risk register score has been adjusted without implementing a response or new evidence.

D:

“Record the actual delay as an issue and assess remaining uncertain consequences as distinct risks” is useful when an event that has already occurred is being managed as an uncertain future risk rather than a current issue. It does not resolve the current problem, in which the risk register score has been adjusted without implementing a response or new evidence.

Question 406

Following the agreed corrective action for this project concern—A laboratory refurbishment team reduces the likelihood score of an asbestos discovery risk but makes no actual change to exposure controls.—which evidence would verify a suitable outcome?

  1. Documented surveys and controls support the new risk score and remaining exposure.
  2. The register identifies accountable oversight and implementable actions with due dates.
  3. The risk register contains a workable contingency with activation criteria and a monitored owner.
  4. A controlled simulation activates the contingency at its agreed threshold.

Explanation

Correct Answer

A:

The strongest confirmation is: Documented surveys and controls support the new risk score and remaining exposure. It is evidence for the specific corrective step—Plan and execute appropriate surveys and containment measures, then reassess residual exposure.—rather than a generic system-health signal.

Incorrect Answers

B:

The observation relates to a problem where the designated risk owner does not have appropriate accountability or decision authority for the response; the required finding here is that documented surveys and controls support the new risk score and remaining exposure.

C:

It would be evidence for a problem in which a material dependency risk has no planned response despite high stage impact. It does not verify that documented surveys and controls support the new risk score and remaining exposure.

D:

This result could confirm a fix when the risk response lacks an executable activation condition and owner. It would not demonstrate that documented surveys and controls support the new risk score and remaining exposure.

Question 407

Which management-control deficiency underlies the following situation? A laboratory refurbishment team reduces the likelihood score of an asbestos discovery risk but makes no actual change to exposure controls.

  1. The risk register score has been adjusted without implementing a response or new evidence.
  2. The risk response lacks an executable activation condition and owner.
  3. Risk management has become a static document instead of an ongoing stage control.
  4. Risk acceptance has bypassed project risk tolerance and the relevant risk decision authority.

Explanation

Correct Answer

A:

The failure is explained by: The risk register score has been adjusted without implementing a response or new evidence. It supports the targeted intervention: Plan and execute appropriate surveys and containment measures, then reassess residual exposure. The observable test of success is: Documented surveys and controls support the new risk score and remaining exposure.

Incorrect Answers

B:

This diagnosis fits a situation in which the risk response lacks an executable activation condition and owner. Here, the risk register score has been adjusted without implementing a response or new evidence.

C:

The cause in this option would matter if risk management has become a static document instead of an ongoing stage control. The reported failure instead arises because the risk register score has been adjusted without implementing a response or new evidence.

D:

The mechanism could explain a fault where risk acceptance has bypassed project risk tolerance and the relevant risk decision authority; it does not account for the current condition, where the risk register score has been adjusted without implementing a response or new evidence.

Question 408

The project team has corrected the following defect: A laboratory refurbishment team reduces the likelihood score of an asbestos discovery risk but makes no actual change to exposure controls. Which future assurance check should be added?

  1. Review risk status and convert realized threats into issue control promptly.
  2. Review risk response triggers in operational readiness exercises.
  3. Test critical single-source supply risks before stage authorization.
  4. Require evidence when risk estimates are reduced after response actions.

Explanation

Correct Answer

D:

This practice reduces the documented recurrence risk: Require evidence when risk estimates are reduced after response actions. The original root fault was: The risk register score has been adjusted without implementing a response or new evidence. The practical health indicator is: Documented surveys and controls support the new risk score and remaining exposure.

Incorrect Answers

A:

This safeguard is useful when an event that has already occurred is being managed as an uncertain future risk rather than a current issue. It does not prevent the present fault, where the risk register score has been adjusted without implementing a response or new evidence.

B:

The option addresses cases in which the risk response lacks an executable activation condition and owner. In the reported incident, the risk register score has been adjusted without implementing a response or new evidence instead.

C:

The proposed routine targets situations in which a material dependency risk has no planned response despite high stage impact. To prevent the reported problem, the team must address the fact that the risk register score has been adjusted without implementing a response or new evidence.

Question 409

The following project-management situation requires a decision: A government data project plans to accept a high-impact cyber threat without asking whether it fits the approved risk appetite. What should the team do?

  1. Plan and execute appropriate surveys and containment measures, then reassess residual exposure.
  2. Compare exposure against agreed tolerance and escalate the proposed acceptance to the authorized decision maker.
  3. Separate the risks and assign tailored preventive or contingent responses to each.
  4. Evaluate alternate capacity responses and any secondary risks before approving the proposed purge.

Explanation

Correct Answer

B:

Compare exposure against agreed tolerance and escalate the proposed acceptance to the authorized decision maker. This is the appropriate intervention because Risk acceptance has bypassed project risk tolerance and the relevant risk decision authority. The specific outcome to verify is: The acceptance or response decision records the applicable tolerance and accountable approval.

Incorrect Answers

A:

When the risk register score has been adjusted without implementing a response or new evidence, “Plan and execute appropriate surveys and containment measures, then reassess residual exposure” could be justified. Here, risk acceptance has bypassed project risk tolerance and the relevant risk decision authority, so this is not the needed correction.

C:

“Separate the risks and assign tailored preventive or contingent responses to each” is useful when distinct threats with different causes and controls have been inappropriately merged. It does not resolve the current problem, in which risk acceptance has bypassed project risk tolerance and the relevant risk decision authority.

D:

When the chosen response creates a new threat that has not been evaluated against project objectives, “Evaluate alternate capacity responses and any secondary risks before approving the proposed purge” could be justified. Here, risk acceptance has bypassed project risk tolerance and the relevant risk decision authority, so this is not the needed correction.

Question 410

For the documented project problem below, which outcome should be verified? A government data project plans to accept a high-impact cyber threat without asking whether it fits the approved risk appetite.

  1. The acceptance or response decision records the applicable tolerance and accountable approval.
  2. An approved option analysis shows the conditional savings and lawful access assumptions.
  3. The risk register cites a defensible evidence basis and revised response priorities.
  4. Current threats and responses are visible in checkpoint and highlight information.

Explanation

Correct Answer

A:

This finding directly demonstrates the intended result: The acceptance or response decision records the applicable tolerance and accountable approval. It tests whether the chosen remediation—Compare exposure against agreed tolerance and escalate the proposed acceptance to the authorized decision maker.—has addressed the cause: Risk acceptance has bypassed project risk tolerance and the relevant risk decision authority.

Incorrect Answers

B:

The observation relates to a problem where the opportunity is recorded as guaranteed rather than assessed for contingent benefits and constraints; the required finding here is that the acceptance or response decision records the applicable tolerance and accountable approval.

C:

The offered finding is relevant when risk assessment is insufficiently evidence-based for a material technical exposure. Here the acceptance test must show that the acceptance or response decision records the applicable tolerance and accountable approval.

D:

That outcome could matter in a case where risk management has become a static document instead of an ongoing stage control, but the present check needs to show that the acceptance or response decision records the applicable tolerance and accountable approval.