Question 210
Following the agreed corrective action for this project concern—An education grant platform is delivered under cost but produces less than half of the forecast verified user benefit.—which evidence would verify a suitable outcome?
Explanation
Correct Answer
Successful remediation is demonstrated when: The end project report separates delivery performance from measured benefit realization and assigns follow-up. That result connects to the targeted action: Report the benefits shortfall, update the final business case and agree an owner-led corrective or follow-up plan. The previously observed defect was: Cost performance is being treated as proof of benefit success even though business outcomes fell short.
Incorrect Answers
The offered finding is relevant when the monitored indicator is a system output rather than the actual end-user benefit. Here the acceptance test must show that the end project report separates delivery performance from measured benefit realization and assigns follow-up.
The offered finding is relevant when the sustainability management approach and post-project measurement ownership are incomplete. Here the acceptance test must show that the end project report separates delivery performance from measured benefit realization and assigns follow-up.
The observation relates to a problem where the additional product option has not been assessed for desirability against existing project objectives; the required finding here is that the end project report separates delivery performance from measured benefit realization and assigns follow-up.