Question 200
Which ongoing review or control is most appropriate for avoiding a repeat of the following project incident? A health-records programme lists multiple expected benefits but no single person accepts responsibility after the project team disbands.
Explanation
Correct Answer
To prevent the same issue, apply this check: Make benefit ownership acceptance a formal project closure handover criterion. The risk to contain is: Post-project benefits responsibility is separated from the operating organization that controls actual realization. Verify control effectiveness using: Each benefit has an agreed measure, named owner and feasible follow-up date.
Incorrect Answers
This measure addresses a risk where the investment decision lacks comparative appraisal of credible options and lifecycle consequences. The recurring failure here arises because post-project benefits responsibility is separated from the operating organization that controls actual realization.
The control would be appropriate if sustainability objectives are not being used as decision criteria alongside scope and cost; the issue here is that post-project benefits responsibility is separated from the operating organization that controls actual realization.
This measure addresses a risk where the benefits profile uses a realization date inconsistent with change adoption prerequisites. The recurring failure here arises because post-project benefits responsibility is separated from the operating organization that controls actual realization.