McAfee-Secured Website

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

100% PRINCE2 PRINCE2 7 Practitioner Guaranteed Success With Testking Training Materials

Get Real PRINCE2 7 Practitioner Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 20

Question 190

A project assurance reviewer validates a response to this scenario: A food inspection programme identifies unexpected equipment disposal impacts but excludes them from its sustainability forecast. What finding supports closure?

  1. The selected option meets recorded ecological criteria or has an explicitly authorized exception.
  2. A post-launch review shows measured queue times against the approved target.
  3. The executive and project board review a net benefit forecast including maintenance over the agreed appraisal period.
  4. The board reviews a quantified disposal impact and an authorized handling plan.

Explanation

Correct Answer

D:

The strongest confirmation is: The board reviews a quantified disposal impact and an authorized handling plan. It is evidence for the specific corrective step—Assess disposal options, update sustainability targets and include their costs in the business case.—rather than a generic system-health signal.

Incorrect Answers

A:

The observation relates to a problem where sustainability objectives are not being used as decision criteria alongside scope and cost; the required finding here is that the board reviews a quantified disposal impact and an authorized handling plan.

B:

That outcome could matter in a case where the monitored indicator is a system output rather than the actual end-user benefit, but the present check needs to show that the board reviews a quantified disposal impact and an authorized handling plan.

C:

The offered finding is relevant when the economic model understates ongoing operating expense and therefore misstates project viability. Here the acceptance test must show that the board reviews a quantified disposal impact and an authorized handling plan.

Question 191

In this project situation, A food inspection programme identifies unexpected equipment disposal impacts but excludes them from its sustainability forecast. What weakness should be corrected?

  1. The sustainability management approach has not captured end-of-life impacts within project decisions.
  2. Post-project benefits responsibility is separated from the operating organization that controls actual realization.
  3. Sustainability objectives are not being used as decision criteria alongside scope and cost.
  4. Cost performance is being treated as proof of benefit success even though business outcomes fell short.

Explanation

Correct Answer

A:

The failure is explained by: The sustainability management approach has not captured end-of-life impacts within project decisions. It supports the targeted intervention: Assess disposal options, update sustainability targets and include their costs in the business case. The observable test of success is: The board reviews a quantified disposal impact and an authorized handling plan.

Incorrect Answers

B:

This diagnosis fits a situation in which post-project benefits responsibility is separated from the operating organization that controls actual realization. Here, the sustainability management approach has not captured end-of-life impacts within project decisions.

C:

This diagnosis fits a situation in which sustainability objectives are not being used as decision criteria alongside scope and cost. Here, the sustainability management approach has not captured end-of-life impacts within project decisions.

D:

There could be such a cause if cost performance is being treated as proof of benefit success even though business outcomes fell short. The stated incident instead arises because the sustainability management approach has not captured end-of-life impacts within project decisions.

Question 192

A Practitioner recommends a permanent improvement after this problem: A food inspection programme identifies unexpected equipment disposal impacts but excludes them from its sustainability forecast. Which control is most effective?

  1. Revalidate external grant conditions as part of stage-boundary business case review.
  2. Schedule benefits reviews based on actual outcomes rather than budget closure alone.
  3. Include end-of-life impacts in sustainability reviews for physical products.
  4. Separate product performance metrics from user benefit metrics in the benefit plan.

Explanation

Correct Answer

C:

This practice reduces the documented recurrence risk: Include end-of-life impacts in sustainability reviews for physical products. The original root fault was: The sustainability management approach has not captured end-of-life impacts within project decisions. The practical health indicator is: The board reviews a quantified disposal impact and an authorized handling plan.

Incorrect Answers

A:

The option addresses cases in which funding eligibility is material to project viability but is missing from stage decision information. In the reported incident, the sustainability management approach has not captured end-of-life impacts within project decisions instead.

B:

The control would be appropriate if cost performance is being treated as proof of benefit success even though business outcomes fell short; the issue here is that the sustainability management approach has not captured end-of-life impacts within project decisions.

D:

This safeguard is useful when the monitored indicator is a system output rather than the actual end-user benefit. It does not prevent the present fault, where the sustainability management approach has not captured end-of-life impacts within project decisions.

Question 193

A project board member examines the following problem: A flood barrier project has a large grant at risk if the next stage misses a legal milestone. Which proposed next step best fits PRINCE2?

  1. Compare the alternative against revised user benefits, cost and risk before asking the board to approve or reject it.
  2. Update the business case's benefit, cost and risk assumptions and present feasible options to the board.
  3. Include grant conditions, likelihood of compliance and funding exposure in the updated business case.
  4. Rephase the benefit forecast and align its measures with actual training and transition readiness milestones.

Explanation

Correct Answer

C:

Include grant conditions, likelihood of compliance and funding exposure in the updated business case. This is the appropriate intervention because Funding eligibility is material to project viability but is missing from stage decision information. The specific outcome to verify is: The stage decision records a tested funding assumption and contingency before authorizing work.

Incorrect Answers

A:

That action tackles a problem where the additional product option has not been assessed for desirability against existing project objectives. The reported issue is instead that funding eligibility is material to project viability but is missing from stage decision information.

B:

That action tackles a problem where material new risk and schedule effects have not been propagated into the current business case. The reported issue is instead that funding eligibility is material to project viability but is missing from stage decision information.

D:

The option would help when the benefits profile uses a realization date inconsistent with change adoption prerequisites, but it would not address a situation where funding eligibility is material to project viability but is missing from stage decision information.

Question 194

Which result best demonstrates appropriate PRINCE2 application in this situation? A flood barrier project has a large grant at risk if the next stage misses a legal milestone.

  1. The updated benefits schedule starts only when operating teams can use the new process.
  2. The stage decision records a tested funding assumption and contingency before authorizing work.
  3. An accountable operator confirms the service budget needed to sustain the planned benefits.
  4. Reported actual service outcomes can be compared with a signed baseline and target after deployment.

Explanation

Correct Answer

B:

This finding directly demonstrates the intended result: The stage decision records a tested funding assumption and contingency before authorizing work. It tests whether the chosen remediation—Include grant conditions, likelihood of compliance and funding exposure in the updated business case.—has addressed the cause: Funding eligibility is material to project viability but is missing from stage decision information.

Incorrect Answers

A:

The offered finding is relevant when the benefits profile uses a realization date inconsistent with change adoption prerequisites. Here the acceptance test must show that the stage decision records a tested funding assumption and contingency before authorizing work.

C:

That outcome could matter in a case where the business case confuses funding for delivery with funding for sustainable operation and benefit realization, but the present check needs to show that the stage decision records a tested funding assumption and contingency before authorizing work.

D:

The observation relates to a problem where the benefits management approach cannot confirm whether the project has achieved its intended outcome; the required finding here is that the stage decision records a tested funding assumption and contingency before authorizing work.

Question 195

The following problem has arisen during a project: A flood barrier project has a large grant at risk if the next stage misses a legal milestone. Which cause fits the evidence?

  1. The sustainability management approach and post-project measurement ownership are incomplete.
  2. Funding eligibility is material to project viability but is missing from stage decision information.
  3. The monitored indicator is a system output rather than the actual end-user benefit.
  4. Post-project benefits responsibility is separated from the operating organization that controls actual realization.

Explanation

Correct Answer

B:

The identified root cause is: Funding eligibility is material to project viability but is missing from stage decision information. The appropriate correction is: Include grant conditions, likelihood of compliance and funding exposure in the updated business case. A separate validation must then show: The stage decision records a tested funding assumption and contingency before authorizing work.

Incorrect Answers

A:

This diagnosis fits a situation in which the sustainability management approach and post-project measurement ownership are incomplete. Here, funding eligibility is material to project viability but is missing from stage decision information.

C:

The cause in this option would matter if the monitored indicator is a system output rather than the actual end-user benefit. The reported failure instead arises because funding eligibility is material to project viability but is missing from stage decision information.

D:

The proposed diagnosis concerns a problem where post-project benefits responsibility is separated from the operating organization that controls actual realization. The facts here indicate that funding eligibility is material to project viability but is missing from stage decision information.

Question 196

What recurring PRINCE2 control would best prevent this situation from happening again? A flood barrier project has a large grant at risk if the next stage misses a legal milestone.

  1. Require measurable baselines and accountable benefit owners in the initiation approval gate.
  2. Trigger business case reviews when new external obligations threaten intended outcomes.
  3. Revalidate external grant conditions as part of stage-boundary business case review.
  4. Include end-of-life impacts in sustainability reviews for physical products.

Explanation

Correct Answer

C:

The lasting control is: Revalidate external grant conditions as part of stage-boundary business case review. It addresses recurrence of this mechanism: Funding eligibility is material to project viability but is missing from stage decision information. A successful system should still demonstrate: The stage decision records a tested funding assumption and contingency before authorizing work.

Incorrect Answers

A:

This safeguard is useful when the benefits management approach cannot confirm whether the project has achieved its intended outcome. It does not prevent the present fault, where funding eligibility is material to project viability but is missing from stage decision information.

B:

This safeguard is useful when material new risk and schedule effects have not been propagated into the current business case. It does not prevent the present fault, where funding eligibility is material to project viability but is missing from stage decision information.

D:

This measure addresses a risk where the sustainability management approach has not captured end-of-life impacts within project decisions. The recurring failure here arises because funding eligibility is material to project viability but is missing from stage decision information.

Question 197

A PRINCE2 Project Management (Version 7) team faces this situation: A health-records programme lists multiple expected benefits but no single person accepts responsibility after the project team disbands. Which corrective governance or delivery action is most appropriate?

  1. Assign appropriate benefit owners, methods and review dates in the benefits management approach.
  2. Document the preferred option against alternatives using whole-life costs, risk and expected benefits.
  3. Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome.
  4. Obtain operational funding commitments and revise the business case before authorizing construction.

Explanation

Correct Answer

A:

The case requires this change: Assign appropriate benefit owners, methods and review dates in the benefits management approach. The actual failure mechanism is: Post-project benefits responsibility is separated from the operating organization that controls actual realization. A meaningful acceptance check is: Each benefit has an agreed measure, named owner and feasible follow-up date.

Incorrect Answers

B:

“Document the preferred option against alternatives using whole-life costs, risk and expected benefits” is useful when the investment decision lacks comparative appraisal of credible options and lifecycle consequences. It does not resolve the current problem, in which post-project benefits responsibility is separated from the operating organization that controls actual realization.

C:

“Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome” is useful when the sustainability management approach and post-project measurement ownership are incomplete. It does not resolve the current problem, in which post-project benefits responsibility is separated from the operating organization that controls actual realization.

D:

When the business case confuses funding for delivery with funding for sustainable operation and benefit realization, “Obtain operational funding commitments and revise the business case before authorizing construction” could be justified. Here, post-project benefits responsibility is separated from the operating organization that controls actual realization, so this is not the needed correction.

Question 198

The project team reports that it resolved the following issue: A health-records programme lists multiple expected benefits but no single person accepts responsibility after the project team disbands. Which observed result is the best acceptance evidence?

  1. The updated benefits schedule starts only when operating teams can use the new process.
  2. Reported actual service outcomes can be compared with a signed baseline and target after deployment.
  3. Each benefit has an agreed measure, named owner and feasible follow-up date.
  4. The executive and project board review a net benefit forecast including maintenance over the agreed appraisal period.

Explanation

Correct Answer

C:

Successful remediation is demonstrated when: Each benefit has an agreed measure, named owner and feasible follow-up date. That result connects to the targeted action: Assign appropriate benefit owners, methods and review dates in the benefits management approach. The previously observed defect was: Post-project benefits responsibility is separated from the operating organization that controls actual realization.

Incorrect Answers

A:

The observation relates to a problem where the benefits profile uses a realization date inconsistent with change adoption prerequisites; the required finding here is that each benefit has an agreed measure, named owner and feasible follow-up date.

B:

It would be evidence for a problem in which the benefits management approach cannot confirm whether the project has achieved its intended outcome. It does not verify that each benefit has an agreed measure, named owner and feasible follow-up date.

D:

The offered finding is relevant when the economic model understates ongoing operating expense and therefore misstates project viability. Here the acceptance test must show that each benefit has an agreed measure, named owner and feasible follow-up date.

Question 199

A Practitioner exam candidate analyses: A health-records programme lists multiple expected benefits but no single person accepts responsibility after the project team disbands. Which diagnosis best accounts for the observed governance failure?

  1. The monitored indicator is a system output rather than the actual end-user benefit.
  2. The investment decision lacks comparative appraisal of credible options and lifecycle consequences.
  3. Material new risk and schedule effects have not been propagated into the current business case.
  4. Post-project benefits responsibility is separated from the operating organization that controls actual realization.

Explanation

Correct Answer

D:

This mechanism accounts for the observation: Post-project benefits responsibility is separated from the operating organization that controls actual realization. Address it by implementing: Assign appropriate benefit owners, methods and review dates in the benefits management approach. Confirm the fix through: Each benefit has an agreed measure, named owner and feasible follow-up date.

Incorrect Answers

A:

The proposed diagnosis concerns a problem where the monitored indicator is a system output rather than the actual end-user benefit. The facts here indicate that post-project benefits responsibility is separated from the operating organization that controls actual realization.

B:

This diagnosis fits a situation in which the investment decision lacks comparative appraisal of credible options and lifecycle consequences. Here, post-project benefits responsibility is separated from the operating organization that controls actual realization.

C:

The cause in this option would matter if material new risk and schedule effects have not been propagated into the current business case. The reported failure instead arises because post-project benefits responsibility is separated from the operating organization that controls actual realization.

Question 200

Which ongoing review or control is most appropriate for avoiding a repeat of the following project incident? A health-records programme lists multiple expected benefits but no single person accepts responsibility after the project team disbands.

  1. Maintain an options appraisal trail for material solution choices.
  2. Include environmental targets among change and stage acceptance measures.
  3. Cross-check benefits timing against the change management and project plans at every boundary.
  4. Make benefit ownership acceptance a formal project closure handover criterion.

Explanation

Correct Answer

D:

To prevent the same issue, apply this check: Make benefit ownership acceptance a formal project closure handover criterion. The risk to contain is: Post-project benefits responsibility is separated from the operating organization that controls actual realization. Verify control effectiveness using: Each benefit has an agreed measure, named owner and feasible follow-up date.

Incorrect Answers

A:

This measure addresses a risk where the investment decision lacks comparative appraisal of credible options and lifecycle consequences. The recurring failure here arises because post-project benefits responsibility is separated from the operating organization that controls actual realization.

B:

The control would be appropriate if sustainability objectives are not being used as decision criteria alongside scope and cost; the issue here is that post-project benefits responsibility is separated from the operating organization that controls actual realization.

C:

This measure addresses a risk where the benefits profile uses a realization date inconsistent with change adoption prerequisites. The recurring failure here arises because post-project benefits responsibility is separated from the operating organization that controls actual realization.