McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 79

Question 780

At a cross-functional software product team, the team wants to avoid repeating: A stakeholder workshop repeatedly includes decision makers who do not understand the topic but excludes the operators doing the work. Which safeguard should it retain?

  1. Separate ideation from decision ranking in workshops.
  2. Check stakeholder relevance before major workshops.
  3. Timebox and record off-topic items for other meetings.
  4. Assign postdelivery benefits accountability at authorization.

Explanation

Correct Answer

B:

Check stakeholder relevance before major workshops. This helps prevent recurrence of: A stakeholder workshop repeatedly includes decision makers who do not understand the topic but excludes the operators doing the work. The required evidence of effective control is: The final decision reflects verified operational constraints and authority.

Incorrect Answers

A:

Separate ideation from decision ranking in workshops. That is a useful control for ANOTHER case: A team rejects unusual design possibilities before exploring options for a new delivery process. The current situation is better prevented by: Check stakeholder relevance before major workshops.

C:

Timebox and record off-topic items for other meetings. That is a useful control for ANOTHER case: A development team has a 15-minute daily coordination slot but spends it revisiting a quarterly budget debate. The current situation is better prevented by: Check stakeholder relevance before major workshops.

D:

Assign postdelivery benefits accountability at authorization. That is a useful control for ANOTHER case: A product launch team attributes declining customer churn to its project but has defined no measurable benefit baseline. The current situation is better prevented by: Check stakeholder relevance before major workshops.

Question 781

A CAPM-level project coordinator sees: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. What is the best next approved step?

  1. Decompose predictive processes into planned activities, dependencies and acceptance gates.
  2. Adapt the predictive governance and evidence workflows to remote stakeholder access and controlled records.
  3. Represent contract approval as a milestone and reserve effort-bearing work packages for actual deliverables.
  4. Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

Explanation

Correct Answer

D:

Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule. This addresses the fictional case: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. The project-management rationale is: External approvals are project constraints that can govern activity order. Verify by: The approved plan shows the permit gate before delivery and commissioning.

Incorrect Answers

A:

Decompose predictive processes into planned activities, dependencies and acceptance gates. This would address a DIFFERENT fictional project situation: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. It is less directly applicable to: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone.

B:

Adapt the predictive governance and evidence workflows to remote stakeholder access and controlled records. This would address a DIFFERENT fictional project situation: A regional construction team uses a fully virtual delivery group but plans only in-person approvals with no digital document control. It is less directly applicable to: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone.

C:

Represent contract approval as a milestone and reserve effort-bearing work packages for actual deliverables. This would address a DIFFERENT fictional project situation: A team calls a zero-effort contract signoff a work package requiring three engineers for two weeks. It is less directly applicable to: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone.

Question 782

For a utilities capital-investment project, what is the strongest acceptance evidence after addressing: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone.

  1. The approved plan shows the permit gate before delivery and commissioning.
  2. Purchase orders reference approved design quantities and stage-gate signoff.
  3. The governance pack shows separate linked scope, schedule, cost and risk controls.
  4. Reports reference the correct approved revision effective date.

Explanation

Correct Answer

A:

The approved plan shows the permit gate before delivery and commissioning. This validates the selected response: Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule. The relevant management principle is: External approvals are project constraints that can govern activity order.

Incorrect Answers

B:

Purchase orders reference approved design quantities and stage-gate signoff. This is evidence for ANOTHER case: A highway rehabilitation has defined engineering packages but the team orders specialized materials before design approval. The specific corrective response here is: Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

C:

The governance pack shows separate linked scope, schedule, cost and risk controls. This is evidence for ANOTHER case: A fixed-budget compliance initiative treats its product requirements list as a substitute for schedule, cost and risk plans. The specific corrective response here is: Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

D:

Reports reference the correct approved revision effective date. This is evidence for ANOTHER case: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The specific corrective response here is: Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

Question 783

A postincident review considers: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. Which principle most directly accounts for the behavior?

  1. Predictive work spans multiple coordinated management processes, not task listing alone.
  2. External approvals are project constraints that can govern activity order.
  3. Organizational structure shapes how a plan-based project coordinates work and approvals.
  4. Good monitoring turns performance evidence into targeted adjustment.

Explanation

Correct Answer

B:

External approvals are project constraints that can govern activity order. This explains the case: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. The targeted action is: Integrate permitting as a predecessor and account for regulatory lead times in the predictive schedule.

Incorrect Answers

A:

Predictive work spans multiple coordinated management processes, not task listing alone. This rationale better explains a DIFFERENT problem: A predictive project owner marks planning complete after listing tasks without defining expected integration, validation or closure activities. The key mechanism for the current situation is: External approvals are project constraints that can govern activity order.

C:

Organizational structure shapes how a plan-based project coordinates work and approvals. This rationale better explains a DIFFERENT problem: A regional construction team uses a fully virtual delivery group but plans only in-person approvals with no digital document control. The key mechanism for the current situation is: External approvals are project constraints that can govern activity order.

D:

Good monitoring turns performance evidence into targeted adjustment. This rationale better explains a DIFFERENT problem: A team logs corrective actions without connecting them to a specific measured deviation. The key mechanism for the current situation is: External approvals are project constraints that can govern activity order.

Question 784

What ongoing preventive practice would most reduce recurrence of: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone.

  1. Confirm decision rights for shared resources at initiation.
  2. Check approval prerequisites in dependency reviews.
  3. Review regulatory dependencies with procurement partners.
  4. Reconcile approvals with financial control ledgers.

Explanation

Correct Answer

C:

Review regulatory dependencies with procurement partners. This helps prevent recurrence of: An offshore supplier's fixed technical deliverable is scheduled without considering the mandatory import permit milestone. The required evidence of effective control is: The approved plan shows the permit gate before delivery and commissioning.

Incorrect Answers

A:

Confirm decision rights for shared resources at initiation. That is a useful control for ANOTHER case: A small hospital project operates in a strong matrix where two functional leaders conflict over a borrowed specialist's priority. The current situation is better prevented by: Review regulatory dependencies with procurement partners.

B:

Check approval prerequisites in dependency reviews. That is a useful control for ANOTHER case: A transit modernization project combines commissioning tests and public activation into one work package despite mandatory test signoff. The current situation is better prevented by: Review regulatory dependencies with procurement partners.

D:

Reconcile approvals with financial control ledgers. That is a useful control for ANOTHER case: A construction cost report omits signed change orders from the controlled cost baseline. The current situation is better prevented by: Review regulatory dependencies with procurement partners.

Question 785

At a distributed delivery organization, the review identifies: A project integrates hardware and software without a plan for managing interface changes between two suppliers. Which response best addresses the specific project management problem?

  1. Include interface integration controls, version coordination and joint acceptance tests in the integrated plan.
  2. Define verification measures, acceptance thresholds and inspection responsibilities.
  3. Forecast a 13-day earliest finish after approved change and updated network logic.
  4. Report positive cost variance $10,000 and investigate the underlying estimate quality.

Explanation

Correct Answer

A:

Include interface integration controls, version coordination and joint acceptance tests in the integrated plan. This addresses the fictional case: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The project-management rationale is: Integration management aligns dependent deliverables into a working whole. Verify by: Supplier interfaces pass controlled integration tests with consistent baselines.

Incorrect Answers

B:

Define verification measures, acceptance thresholds and inspection responsibilities. This would address a DIFFERENT fictional project situation: A project promises that testing will be excellent but the quality plan includes no measurable thresholds. It is less directly applicable to: A project integrates hardware and software without a plan for managing interface changes between two suppliers.

C:

Forecast a 13-day earliest finish after approved change and updated network logic. This would address a DIFFERENT fictional project situation: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration. It is less directly applicable to: A project integrates hardware and software without a plan for managing interface changes between two suppliers.

D:

Report positive cost variance $10,000 and investigate the underlying estimate quality. This would address a DIFFERENT fictional project situation: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. It is less directly applicable to: A project integrates hardware and software without a plan for managing interface changes between two suppliers.

Question 786

The project issue was: A project integrates hardware and software without a plan for managing interface changes between two suppliers. Which outcome demonstrates that its remedy worked?

  1. Each scheduled activity traces to an accepted WBS work package.
  2. Supplier interfaces pass controlled integration tests with consistent baselines.
  3. Release readiness is blocked until documented signoff.
  4. The cost-control report identifies the deficit accurately.

Explanation

Correct Answer

B:

Supplier interfaces pass controlled integration tests with consistent baselines. This validates the selected response: Include interface integration controls, version coordination and joint acceptance tests in the integrated plan. The relevant management principle is: Integration management aligns dependent deliverables into a working whole.

Incorrect Answers

A:

Each scheduled activity traces to an accepted WBS work package. This is evidence for ANOTHER case: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. The specific corrective response here is: Include interface integration controls, version coordination and joint acceptance tests in the integrated plan.

C:

Release readiness is blocked until documented signoff. This is evidence for ANOTHER case: A predictive schedule includes procurement, design and testing but omits the software security signoff needed before release. The specific corrective response here is: Include interface integration controls, version coordination and joint acceptance tests in the integrated plan.

D:

The cost-control report identifies the deficit accurately. This is evidence for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The specific corrective response here is: Include interface integration controls, version coordination and joint acceptance tests in the integrated plan.

Question 787

For a distributed delivery organization, the documented failure was: A project integrates hardware and software without a plan for managing interface changes between two suppliers. Which explanation is most accurate?

  1. Work packages support estimating, control and accountability at an appropriate level.
  2. WBS decomposition defines scope deliverables rather than merely replicating time sheets.
  3. Integration management aligns dependent deliverables into a working whole.
  4. Organizational structure shapes how a plan-based project coordinates work and approvals.

Explanation

Correct Answer

C:

Integration management aligns dependent deliverables into a working whole. This explains the case: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The targeted action is: Include interface integration controls, version coordination and joint acceptance tests in the integrated plan.

Incorrect Answers

A:

Work packages support estimating, control and accountability at an appropriate level. This rationale better explains a DIFFERENT problem: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The key mechanism for the current situation is: Integration management aligns dependent deliverables into a working whole.

B:

WBS decomposition defines scope deliverables rather than merely replicating time sheets. This rationale better explains a DIFFERENT problem: A contractor divides an installation project into 400 individual time entries but cannot map them to any controllable deliverables. The key mechanism for the current situation is: Integration management aligns dependent deliverables into a working whole.

D:

Organizational structure shapes how a plan-based project coordinates work and approvals. This rationale better explains a DIFFERENT problem: A regional construction team uses a fully virtual delivery group but plans only in-person approvals with no digital document control. The key mechanism for the current situation is: Integration management aligns dependent deliverables into a working whole.

Question 788

Which recurring governance check best addresses the risk of repeating: A project integrates hardware and software without a plan for managing interface changes between two suppliers.

  1. Review sign conventions with project analysts.
  2. Reject unverifiable single-package baselines for complex scopes.
  3. Record shared-resource agreements before major assignments.
  4. Audit cross-vendor interface agreements before testing.

Explanation

Correct Answer

D:

Audit cross-vendor interface agreements before testing. This helps prevent recurrence of: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The required evidence of effective control is: Supplier interfaces pass controlled integration tests with consistent baselines.

Incorrect Answers

A:

Review sign conventions with project analysts. That is a useful control for ANOTHER case: An engineering project has earned value $75,000 and planned value $60,000 but staff report 15,000 dollars behind schedule. The current situation is better prevented by: Audit cross-vendor interface agreements before testing.

B:

Reject unverifiable single-package baselines for complex scopes. That is a useful control for ANOTHER case: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The current situation is better prevented by: Audit cross-vendor interface agreements before testing.

C:

Record shared-resource agreements before major assignments. That is a useful control for ANOTHER case: A functional department loans staff to a project without acknowledging the project's fixed schedule responsibilities. The current situation is better prevented by: Audit cross-vendor interface agreements before testing.

Question 789

During a project review, stakeholders report: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. What should the team do first?

  1. Report positive cost variance $10,000 and investigate the underlying estimate quality.
  2. Apply the authorized baseline revision and retain immutable earlier versions for audit.
  3. Use EV−AC for cost variance and track PV separately for schedule variance.
  4. Maintain the distinct integrated project execution plans and product requirements baseline.

Explanation

Correct Answer

B:

Apply the authorized baseline revision and retain immutable earlier versions for audit. This addresses the fictional case: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The project-management rationale is: Predictive variance must compare against legitimate current baselines. Verify by: Reports reference the correct approved revision effective date.

Incorrect Answers

A:

Report positive cost variance $10,000 and investigate the underlying estimate quality. This would address a DIFFERENT fictional project situation: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. It is less directly applicable to: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless.

C:

Use EV−AC for cost variance and track PV separately for schedule variance. This would address a DIFFERENT fictional project situation: A project status sheet calculates cost variance as PV−AC, masking the fact that earned value is lower than planned. It is less directly applicable to: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless.

D:

Maintain the distinct integrated project execution plans and product requirements baseline. This would address a DIFFERENT fictional project situation: A fixed-budget compliance initiative treats its product requirements list as a substitute for schedule, cost and risk plans. It is less directly applicable to: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless.

Question 790

Following the proposed correction, what observation confirms success: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless.

  1. The report shows SV −$20,000 and an explained mitigation proposal.
  2. EV and AC reconciliation shows CV = +$10,000.
  3. Reports reference the correct approved revision effective date.
  4. A reviewable schedule links procurement, installation and inspection in the required order.

Explanation

Correct Answer

C:

Reports reference the correct approved revision effective date. This validates the selected response: Apply the authorized baseline revision and retain immutable earlier versions for audit. The relevant management principle is: Predictive variance must compare against legitimate current baselines.

Incorrect Answers

A:

The report shows SV −$20,000 and an explained mitigation proposal. This is evidence for ANOTHER case: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.

B:

EV and AC reconciliation shows CV = +$10,000. This is evidence for ANOTHER case: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.

D:

A reviewable schedule links procurement, installation and inspection in the required order. This is evidence for ANOTHER case: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.