Question 760
For the previous project issue, select the best preventive control: A BA confirms that all backlog stories have a Done label but the release lacks the approved interface to a partner platform.
Explanation
Correct Answer
Include integration dependencies in release gate reviews. This helps prevent recurrence of: A BA confirms that all backlog stories have a Done label but the release lacks the approved interface to a partner platform. The required evidence of effective control is: Partner integration is validated end to end before readiness approval.
Incorrect Answers
Require customer-visible acceptance measures in contracts. That is a useful control for ANOTHER case: A sponsor asks the BA to accept a feature because the vendor says it is complete, but no user criteria were recorded. The current situation is better prevented by: Include integration dependencies in release gate reviews.
Include nontechnical deliverables in acceptance mapping. That is a useful control for ANOTHER case: A predictive project installs equipment but signs final acceptance before required operational training is delivered. The current situation is better prevented by: Include integration dependencies in release gate reviews.
Reserve BA capacity throughout iteration cycles. That is a useful control for ANOTHER case: An agile team freezes business analysis until a six-month requirements document is signed, delaying feedback from early increments. The current situation is better prevented by: Include integration dependencies in release gate reviews.