Question 790
Following the proposed correction, what observation confirms success: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless.
Explanation
Correct Answer
Reports reference the correct approved revision effective date. This validates the selected response: Apply the authorized baseline revision and retain immutable earlier versions for audit. The relevant management principle is: Predictive variance must compare against legitimate current baselines.
Incorrect Answers
The report shows SV −$20,000 and an explained mitigation proposal. This is evidence for ANOTHER case: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.
EV and AC reconciliation shows CV = +$10,000. This is evidence for ANOTHER case: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.
A reviewable schedule links procurement, installation and inspection in the required order. This is evidence for ANOTHER case: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. The specific corrective response here is: Apply the authorized baseline revision and retain immutable earlier versions for audit.