Question 40
For the previous project issue, select the best preventive control: A two-week sprint begins without a selected goal and developers start ten unrelated backlog items.
Explanation
Correct Answer
Require goal clarity in sprint planning. This helps prevent recurrence of: A two-week sprint begins without a selected goal and developers start ten unrelated backlog items. The required evidence of effective control is: The sprint review demonstrates a coherent usable outcome against the planned goal.
Incorrect Answers
Refine oversized stories before iteration commitment. That is a useful control for ANOTHER case: A team says each user story must be one entire quarter in duration and cannot be split. The current situation is better prevented by: Require goal clarity in sprint planning.
Identify risky interfaces during backlog refinement. That is a useful control for ANOTHER case: A product owner sets iteration scope using only estimated hours and ignores a high-risk external integration dependency. The current situation is better prevented by: Require goal clarity in sprint planning.
Review expedited work frequency and impact. That is a useful control for ANOTHER case: A Kanban team has urgent requests interrupting every task with no explicit expedite policy. The current situation is better prevented by: Require goal clarity in sprint planning.