Question 510
The storage reliability team at Silver Cove Payments are responsible for settlement data volumes and secure backups. Their assessment shows: A site-level recovery plan restores the replicated volume but neglects protocol LIFs, SVM networking and client DNS records. The team reports that the correction is complete. Which observation BEST proves the stated problem is resolved?
Explanation
Correct Answer
A representative client mounts the recovered file service through an approved network route after failover. The observation verifies that the chosen action (Include SVM and client access reconfiguration in the end-to-end recovery runbook) has corrected the initiating failure (A site-level recovery plan restores the replicated volume but neglects protocol LIFs, SVM networking and client DNS records). This is directly measurable for Silver Cove Payments's settlement data volumes and secure backups rather than merely reporting task completion.
Incorrect Answers
A controlled site-failure simulation maintains or restores service within defined RPO and RTO. This is a valid test for another condition (A mission-critical application requires near-zero interruption after a site outage but the plan provides only asynchronous once-daily SnapMirror updates) after a different correction (Evaluate a supported synchronous or SnapMirror active sync design appropriate to host and platform constraints). It does not establish the necessary result for Silver Cove Payments's settlement data volumes and secure backups: A representative client mounts the recovered file service through an approved network route after failover.
The design documents which node or site failures each mechanism covers and proves the selected recovery path. This is a valid test for another condition (A regional continuity plan refers to MetroCluster and ordinary local HA as interchangeable solutions) after a different correction (Match MetroCluster architecture and distance or quorum prerequisites to actual site-level continuity requirements). It does not establish the necessary result for Silver Cove Payments's settlement data volumes and secure backups: A representative client mounts the recovered file service through an approved network route after failover.
An application transaction passes after failover and recorded outage duration meets the agreed target. This is a valid test for another condition (A business-continuity test exercises storage access alone and ignores whether the application can complete transactions after failover) after a different correction (Define application-level integrity and transaction probes as continuity acceptance criteria). It does not establish the necessary result for Silver Cove Payments's settlement data volumes and secure backups: A representative client mounts the recovered file service through an approved network route after failover.