Question 80
A project governance review at Sundown Freight identifies this problem during a product deployment planning session: A customer demands a fixed specification and formal acceptance before procurement but a vendor offers only an undefined adaptive backlog. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
A selected delivery method includes testable acceptance criteria and agreed change-control mechanisms. This is the relevant acceptance evidence because it tests whether the corrective action (Evaluate whether a predictive contractual baseline better fits fixed acceptance and procurement constraints.) fixed the original concern (A customer demands a fixed specification and formal acceptance before procurement but a vendor offers only an undefined adaptive backlog.) at Sundown Freight, rather than relying only on a task marked complete. The affected work concerns transport systems and partner document access.
Incorrect Answers
The next sprint plan incorporates approved priority changes while current scope is managed transparently. This evidence would be useful for another condition (A Scrum team repeatedly changes the sprint goal mid-iteration without product-owner discussion when requests arrive.) and its different action (Protect the agreed sprint goal and route changed priorities to appropriate product backlog planning.). At Sundown Freight, it does not demonstrate the required project outcome: A selected delivery method includes testable acceptance criteria and agreed change-control mechanisms.
Meeting records show daily blockers handled by the team while funding approval remains with governance. This evidence would be useful for another condition (An Agile team's daily standup is used to approve project funding and replace the sponsor's formal business governance.) and its different action (Separate short team coordination from the sponsor's authorization and financial decisions.). At Sundown Freight, it does not demonstrate the required project outcome: A selected delivery method includes testable acceptance criteria and agreed change-control mechanisms.
The change request documents impact and approval before a new baseline is issued. This evidence would be useful for another condition (A team using fixed sequential design reviews discovers a new requirement but inserts it directly into a signed-off phase without analysis.) and its different action (Apply formal predictive change control before altering the approved downstream deliverables.). At Sundown Freight, it does not demonstrate the required project outcome: A selected delivery method includes testable acceptance criteria and agreed change-control mechanisms.