Question 90
A project affecting subscriber applications and remote operations at Orion Network Services encounters a management concern: An executive decides Agile means no documentation is needed even when a regulated system requires traceability of approvals. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
An auditor traces delivered functionality to approved requirements even though releases are iterative. This is the relevant acceptance evidence because it tests whether the corrective action (Maintain documentation and control evidence proportionate to the project's risk and compliance needs.) fixed the original concern (An executive decides Agile means no documentation is needed even when a regulated system requires traceability of approvals.) at Orion Network Services, rather than relying only on a task marked complete. The affected work concerns subscriber applications and remote operations.
Incorrect Answers
Meeting records show daily blockers handled by the team while funding approval remains with governance. This evidence would be useful for another condition (An Agile team's daily standup is used to approve project funding and replace the sponsor's formal business governance.) and its different action (Separate short team coordination from the sponsor's authorization and financial decisions.). At Orion Network Services, it does not demonstrate the required project outcome: An auditor traces delivered functionality to approved requirements even though releases are iterative.
The change request documents impact and approval before a new baseline is issued. This evidence would be useful for another condition (A team using fixed sequential design reviews discovers a new requirement but inserts it directly into a signed-off phase without analysis.) and its different action (Apply formal predictive change control before altering the approved downstream deliverables.). At Orion Network Services, it does not demonstrate the required project outcome: An auditor traces delivered functionality to approved requirements even though releases are iterative.
The approved delivery approach records which constraint can adapt and which approvals control it. This evidence would be useful for another condition (A sponsor insists on changing project requirements every day while requiring the cost and end date to stay absolutely fixed.) and its different action (Assess change tolerance and explain the tradeoffs among scope schedule and budget before selecting an approach.). At Orion Network Services, it does not demonstrate the required project outcome: An auditor traces delivered functionality to approved requirements even though releases are iterative.