Question 60
A project governance review at Atlas Scientific identifies this problem during a high-priority issue escalation: A sponsor insists on changing project requirements every day while requiring the cost and end date to stay absolutely fixed. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The approved delivery approach records which constraint can adapt and which approvals control it. This is the relevant acceptance evidence because it tests whether the corrective action (Assess change tolerance and explain the tradeoffs among scope schedule and budget before selecting an approach.) fixed the original concern (A sponsor insists on changing project requirements every day while requiring the cost and end date to stay absolutely fixed.) at Atlas Scientific, rather than relying only on a task marked complete. The affected work concerns lab collaboration and cloud-hosted research.
Incorrect Answers
The change request documents impact and approval before a new baseline is issued. This evidence would be useful for another condition (A team using fixed sequential design reviews discovers a new requirement but inserts it directly into a signed-off phase without analysis.) and its different action (Apply formal predictive change control before altering the approved downstream deliverables.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved delivery approach records which constraint can adapt and which approvals control it.
A selected delivery method includes testable acceptance criteria and agreed change-control mechanisms. This evidence would be useful for another condition (A customer demands a fixed specification and formal acceptance before procurement but a vendor offers only an undefined adaptive backlog.) and its different action (Evaluate whether a predictive contractual baseline better fits fixed acceptance and procurement constraints.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved delivery approach records which constraint can adapt and which approvals control it.
Meeting records show daily blockers handled by the team while funding approval remains with governance. This evidence would be useful for another condition (An Agile team's daily standup is used to approve project funding and replace the sponsor's formal business governance.) and its different action (Separate short team coordination from the sponsor's authorization and financial decisions.). At Atlas Scientific, it does not demonstrate the required project outcome: The approved delivery approach records which constraint can adapt and which approvals control it.