McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 78

Question 770

For Brightstone Legal, the implementation team reports the following delivery problem: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A sampled requirement has a traceable test case status and responsible owner.
  2. A selected scope change has one traceable decision and closure record.
  3. The board shows the current owner and state of each work item.
  4. The network identifies the controlling sequence and the effect of delaying a critical activity.

Explanation

Correct Answer

A:

A sampled requirement has a traceable test case status and responsible owner. This is the relevant acceptance evidence because it tests whether the corrective action (Maintain a requirements traceability matrix linking needs designs and acceptance tests.) fixed the original concern (An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand.) at Brightstone Legal, rather than relying only on a task marked complete. The affected work concerns matter files and sensitive case records.

Incorrect Answers

B:

A selected scope change has one traceable decision and closure record. This evidence would be useful for another condition (A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails.) and its different action (Maintain a controlled change log with identifiers impacts approvals and implementation status.). At Brightstone Legal, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

C:

The board shows the current owner and state of each work item. This evidence would be useful for another condition (The project team needs to track work item movement through analysis build and review but reports only aggregate hours.) and its different action (Use a task board with visible workflow states ownership and blocked-item indicators.). At Brightstone Legal, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

D:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Brightstone Legal, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

Question 771

At Oceanview Payments, the delivery assessment finds: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. Which project management action BEST addresses the particular issue?

  1. Maintain a controlled change log with identifiers impacts approvals and implementation status.
  2. Maintain a requirements traceability matrix linking needs designs and acceptance tests.
  3. Use a project network diagram with dependencies and critical path analysis.
  4. Use a task board with visible workflow states ownership and blocked-item indicators.

Explanation

Correct Answer

B:

Maintain a requirements traceability matrix linking needs designs and acceptance tests. This directly addresses the reported management gap: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. For Oceanview Payments and its regulated card workflows and employee access, a useful verification outcome is: A sampled requirement has a traceable test case status and responsible owner.

Incorrect Answers

A:

Maintain a controlled change log with identifiers impacts approvals and implementation status. This choice addresses another specific project condition: A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails. The actual issue at Oceanview Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

C:

Use a project network diagram with dependencies and critical path analysis. This choice addresses another specific project condition: A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines. The actual issue at Oceanview Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

D:

Use a task board with visible workflow states ownership and blocked-item indicators. This choice addresses another specific project condition: The project team needs to track work item movement through analysis build and review but reports only aggregate hours. The actual issue at Oceanview Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

Question 772

At Oceanview Payments, the delivery assessment finds: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A selected scope change has one traceable decision and closure record.
  2. A sampled requirement has a traceable test case status and responsible owner.
  3. The board shows the current owner and state of each work item.
  4. The network identifies the controlling sequence and the effect of delaying a critical activity.

Explanation

Correct Answer

B:

A sampled requirement has a traceable test case status and responsible owner. This is the relevant acceptance evidence because it tests whether the corrective action (Maintain a requirements traceability matrix linking needs designs and acceptance tests.) fixed the original concern (An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand.) at Oceanview Payments, rather than relying only on a task marked complete. The affected work concerns regulated card workflows and employee access.

Incorrect Answers

A:

A selected scope change has one traceable decision and closure record. This evidence would be useful for another condition (A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails.) and its different action (Maintain a controlled change log with identifiers impacts approvals and implementation status.). At Oceanview Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

C:

The board shows the current owner and state of each work item. This evidence would be useful for another condition (The project team needs to track work item movement through analysis build and review but reports only aggregate hours.) and its different action (Use a task board with visible workflow states ownership and blocked-item indicators.). At Oceanview Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

D:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Oceanview Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

Question 773

Silver Cove Payments is delivering an IT initiative involving transaction data and fraud monitoring in a mixed Agile and predictive delivery environment. The team observes: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. Which project management action BEST addresses the particular issue?

  1. Maintain a controlled change log with identifiers impacts approvals and implementation status.
  2. Use a task board with visible workflow states ownership and blocked-item indicators.
  3. Maintain a requirements traceability matrix linking needs designs and acceptance tests.
  4. Use a project network diagram with dependencies and critical path analysis.

Explanation

Correct Answer

C:

Maintain a requirements traceability matrix linking needs designs and acceptance tests. This directly addresses the reported management gap: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. For Silver Cove Payments and its transaction data and fraud monitoring, a useful verification outcome is: A sampled requirement has a traceable test case status and responsible owner.

Incorrect Answers

A:

Maintain a controlled change log with identifiers impacts approvals and implementation status. This choice addresses another specific project condition: A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails. The actual issue at Silver Cove Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

B:

Use a task board with visible workflow states ownership and blocked-item indicators. This choice addresses another specific project condition: The project team needs to track work item movement through analysis build and review but reports only aggregate hours. The actual issue at Silver Cove Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

D:

Use a project network diagram with dependencies and critical path analysis. This choice addresses another specific project condition: A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines. The actual issue at Silver Cove Payments is: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. That other intervention does not itself establish the required result: A sampled requirement has a traceable test case status and responsible owner.

Question 774

Silver Cove Payments is delivering an IT initiative involving transaction data and fraud monitoring in a mixed Agile and predictive delivery environment. The team observes: An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The board shows the current owner and state of each work item.
  2. The network identifies the controlling sequence and the effect of delaying a critical activity.
  3. A sampled requirement has a traceable test case status and responsible owner.
  4. A selected scope change has one traceable decision and closure record.

Explanation

Correct Answer

C:

A sampled requirement has a traceable test case status and responsible owner. This is the relevant acceptance evidence because it tests whether the corrective action (Maintain a requirements traceability matrix linking needs designs and acceptance tests.) fixed the original concern (An audit asks which requirements have corresponding tests and the PM searches loosely named spreadsheets by hand.) at Silver Cove Payments, rather than relying only on a task marked complete. The affected work concerns transaction data and fraud monitoring.

Incorrect Answers

A:

The board shows the current owner and state of each work item. This evidence would be useful for another condition (The project team needs to track work item movement through analysis build and review but reports only aggregate hours.) and its different action (Use a task board with visible workflow states ownership and blocked-item indicators.). At Silver Cove Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

B:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Silver Cove Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

D:

A selected scope change has one traceable decision and closure record. This evidence would be useful for another condition (A project manager needs a formal record of proposed scope modifications but stores change requests as unrelated emails.) and its different action (Maintain a controlled change log with identifiers impacts approvals and implementation status.). At Silver Cove Payments, it does not demonstrate the required project outcome: A sampled requirement has a traceable test case status and responsible owner.

Question 775

Crescent Education is delivering an IT initiative involving learning platforms and staff accounts under controlled release and records requirements. The team observes: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. Which project management action BEST addresses the particular issue?

  1. Use a project network diagram with dependencies and critical path analysis.
  2. Track the issue in a structured issue log with severity responsibility and progress notes.
  3. Build a Gantt chart from scheduled tasks dependencies and milestones.
  4. Use separate issue tracking and risk register entries with appropriate owners and responses.

Explanation

Correct Answer

D:

Use separate issue tracking and risk register entries with appropriate owners and responses. This directly addresses the reported management gap: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. For Crescent Education and its learning platforms and staff accounts, a useful verification outcome is: A reviewer can distinguish a current blocker from an event that might occur in the future.

Incorrect Answers

A:

Use a project network diagram with dependencies and critical path analysis. This choice addresses another specific project condition: A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines. The actual issue at Crescent Education is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

B:

Track the issue in a structured issue log with severity responsibility and progress notes. This choice addresses another specific project condition: An open issue is assigned to a team but has no priority owner due date or history of follow-up. The actual issue at Crescent Education is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

C:

Build a Gantt chart from scheduled tasks dependencies and milestones. This choice addresses another specific project condition: A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list. The actual issue at Crescent Education is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

Question 776

Crescent Education is delivering an IT initiative involving learning platforms and staff accounts under controlled release and records requirements. The team observes: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The next review can identify the owner latest action and agreed resolution date.
  2. A reviewer can distinguish a current blocker from an event that might occur in the future.
  3. The sponsor can identify start finish and overlap of work on the approved time axis.
  4. The network identifies the controlling sequence and the effect of delaying a critical activity.

Explanation

Correct Answer

B:

A reviewer can distinguish a current blocker from an event that might occur in the future. This is the relevant acceptance evidence because it tests whether the corrective action (Use separate issue tracking and risk register entries with appropriate owners and responses.) fixed the original concern (The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties.) at Crescent Education, rather than relying only on a task marked complete. The affected work concerns learning platforms and staff accounts.

Incorrect Answers

A:

The next review can identify the owner latest action and agreed resolution date. This evidence would be useful for another condition (An open issue is assigned to a team but has no priority owner due date or history of follow-up.) and its different action (Track the issue in a structured issue log with severity responsibility and progress notes.). At Crescent Education, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

C:

The sponsor can identify start finish and overlap of work on the approved time axis. This evidence would be useful for another condition (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) and its different action (Build a Gantt chart from scheduled tasks dependencies and milestones.). At Crescent Education, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

D:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Crescent Education, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

Question 777

For Newbridge Charity, the business analyst reports the following delivery problem: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. Which project management action BEST addresses the particular issue?

  1. Use a project network diagram with dependencies and critical path analysis.
  2. Use separate issue tracking and risk register entries with appropriate owners and responses.
  3. Build a Gantt chart from scheduled tasks dependencies and milestones.
  4. Track the issue in a structured issue log with severity responsibility and progress notes.

Explanation

Correct Answer

B:

Use separate issue tracking and risk register entries with appropriate owners and responses. This directly addresses the reported management gap: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. For Newbridge Charity and its donation workflows and volunteer accounts, a useful verification outcome is: A reviewer can distinguish a current blocker from an event that might occur in the future.

Incorrect Answers

A:

Use a project network diagram with dependencies and critical path analysis. This choice addresses another specific project condition: A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines. The actual issue at Newbridge Charity is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

C:

Build a Gantt chart from scheduled tasks dependencies and milestones. This choice addresses another specific project condition: A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list. The actual issue at Newbridge Charity is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

D:

Track the issue in a structured issue log with severity responsibility and progress notes. This choice addresses another specific project condition: An open issue is assigned to a team but has no priority owner due date or history of follow-up. The actual issue at Newbridge Charity is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

Question 778

For Newbridge Charity, the business analyst reports the following delivery problem: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The next review can identify the owner latest action and agreed resolution date.
  2. The sponsor can identify start finish and overlap of work on the approved time axis.
  3. A reviewer can distinguish a current blocker from an event that might occur in the future.
  4. The network identifies the controlling sequence and the effect of delaying a critical activity.

Explanation

Correct Answer

C:

A reviewer can distinguish a current blocker from an event that might occur in the future. This is the relevant acceptance evidence because it tests whether the corrective action (Use separate issue tracking and risk register entries with appropriate owners and responses.) fixed the original concern (The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties.) at Newbridge Charity, rather than relying only on a task marked complete. The affected work concerns donation workflows and volunteer accounts.

Incorrect Answers

A:

The next review can identify the owner latest action and agreed resolution date. This evidence would be useful for another condition (An open issue is assigned to a team but has no priority owner due date or history of follow-up.) and its different action (Track the issue in a structured issue log with severity responsibility and progress notes.). At Newbridge Charity, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

B:

The sponsor can identify start finish and overlap of work on the approved time axis. This evidence would be useful for another condition (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) and its different action (Build a Gantt chart from scheduled tasks dependencies and milestones.). At Newbridge Charity, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

D:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Newbridge Charity, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

Question 779

At Greenpeak Civic Services, the delivery assessment finds: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. Which project management action BEST addresses the particular issue?

  1. Use separate issue tracking and risk register entries with appropriate owners and responses.
  2. Use a project network diagram with dependencies and critical path analysis.
  3. Track the issue in a structured issue log with severity responsibility and progress notes.
  4. Build a Gantt chart from scheduled tasks dependencies and milestones.

Explanation

Correct Answer

A:

Use separate issue tracking and risk register entries with appropriate owners and responses. This directly addresses the reported management gap: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. For Greenpeak Civic Services and its citizen services and digital identity, a useful verification outcome is: A reviewer can distinguish a current blocker from an event that might occur in the future.

Incorrect Answers

B:

Use a project network diagram with dependencies and critical path analysis. This choice addresses another specific project condition: A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines. The actual issue at Greenpeak Civic Services is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

C:

Track the issue in a structured issue log with severity responsibility and progress notes. This choice addresses another specific project condition: An open issue is assigned to a team but has no priority owner due date or history of follow-up. The actual issue at Greenpeak Civic Services is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

D:

Build a Gantt chart from scheduled tasks dependencies and milestones. This choice addresses another specific project condition: A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list. The actual issue at Greenpeak Civic Services is: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. That other intervention does not itself establish the required result: A reviewer can distinguish a current blocker from an event that might occur in the future.

Question 780

At Greenpeak Civic Services, the delivery assessment finds: The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The next review can identify the owner latest action and agreed resolution date.
  2. The network identifies the controlling sequence and the effect of delaying a critical activity.
  3. The sponsor can identify start finish and overlap of work on the approved time axis.
  4. A reviewer can distinguish a current blocker from an event that might occur in the future.

Explanation

Correct Answer

D:

A reviewer can distinguish a current blocker from an event that might occur in the future. This is the relevant acceptance evidence because it tests whether the corrective action (Use separate issue tracking and risk register entries with appropriate owners and responses.) fixed the original concern (The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties.) at Greenpeak Civic Services, rather than relying only on a task marked complete. The affected work concerns citizen services and digital identity.

Incorrect Answers

A:

The next review can identify the owner latest action and agreed resolution date. This evidence would be useful for another condition (An open issue is assigned to a team but has no priority owner due date or history of follow-up.) and its different action (Track the issue in a structured issue log with severity responsibility and progress notes.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

B:

The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.

C:

The sponsor can identify start finish and overlap of work on the approved time axis. This evidence would be useful for another condition (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) and its different action (Build a Gantt chart from scheduled tasks dependencies and milestones.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: A reviewer can distinguish a current blocker from an event that might occur in the future.