Question 760
For Evergreen Hospital, the delivery lead reports the following delivery problem: A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The sponsor can identify start finish and overlap of work on the approved time axis. This is the relevant acceptance evidence because it tests whether the corrective action (Build a Gantt chart from scheduled tasks dependencies and milestones.) fixed the original concern (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) at Evergreen Hospital, rather than relying only on a task marked complete. The affected work concerns care coordination and staff identity services.
Incorrect Answers
The chart separates progress on delivered work from additions to overall scope. This evidence would be useful for another condition (Leadership wants to see how much scope has been delivered while total product scope has grown during the iteration.) and its different action (Use a burnup chart showing completed work against the changing total-scope line.). At Evergreen Hospital, it does not demonstrate the required project outcome: The sponsor can identify start finish and overlap of work on the approved time axis.
The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Evergreen Hospital, it does not demonstrate the required project outcome: The sponsor can identify start finish and overlap of work on the approved time axis.
A reviewer can distinguish a current blocker from an event that might occur in the future. This evidence would be useful for another condition (The PM keeps active blockers and potential threats in one list without distinguishing realized events from uncertainties.) and its different action (Use separate issue tracking and risk register entries with appropriate owners and responses.). At Evergreen Hospital, it does not demonstrate the required project outcome: The sponsor can identify start finish and overlap of work on the approved time axis.