Question 790
At Cobalt Aerospace, the delivery assessment finds: Developers keep overwriting the latest approved specification in shared folders with no way to compare changes. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
A reviewer can retrieve the earlier approved specification and identify who changed it. This is the relevant acceptance evidence because it tests whether the corrective action (Use version control with attributable revisions and an agreed release branch.) fixed the original concern (Developers keep overwriting the latest approved specification in shared folders with no way to compare changes.) at Cobalt Aerospace, rather than relying only on a task marked complete. The affected work concerns engineering programs and secure collaboration.
Incorrect Answers
The chart shows actual remaining work and makes deviations from the ideal trend visible. This evidence would be useful for another condition (An Agile release is halfway through but the team cannot forecast remaining work because it records only total stories ever completed.) and its different action (Use a burndown chart comparing remaining planned work with sprint time.). At Cobalt Aerospace, it does not demonstrate the required project outcome: A reviewer can retrieve the earlier approved specification and identify who changed it.
The sponsor can identify start finish and overlap of work on the approved time axis. This evidence would be useful for another condition (A PM wants to see planned activities as horizontal bars against calendar dates but uses an unstructured issue list.) and its different action (Build a Gantt chart from scheduled tasks dependencies and milestones.). At Cobalt Aerospace, it does not demonstrate the required project outcome: A reviewer can retrieve the earlier approved specification and identify who changed it.
The network identifies the controlling sequence and the effect of delaying a critical activity. This evidence would be useful for another condition (A steering group asks which planned activities control the project completion date but the team provides only a list of deadlines.) and its different action (Use a project network diagram with dependencies and critical path analysis.). At Cobalt Aerospace, it does not demonstrate the required project outcome: A reviewer can retrieve the earlier approved specification and identify who changed it.